7
Q:

A tank has an inlet and outlet pipe. The inlet pipe fills the tank completely in 2 hours when the outlet pipe is plugged. The outlet pipe empties the tank completely in 6 hours when the inlet pipe is pluggeed.

If there is a lekage also which is capable of draining out the liquid from the tank at half of the  rate of outet pipe,them what is the time taken to fill the emty tank when both the pipes are opened?

A) 3 hours B) 4 hours
C) 5 hours D) None of these

Answer:   B) 4 hours



Explanation:

Rate of leakage = 8.33% per hour

Net efficiency = 50 - (16.66 + 8.33)= 25%

Time required = 100/25 = 4 hours

Q:

P is 30% more efficient than Q. How much time will they, working together, take to complete a job which P alone could have done in 23 days?

A) 16 days B) 13 days
C) 15 days D) 12 days
 
Answer & Explanation Answer: B) 13 days

Explanation:

Ratio of times taken by P & Q = 100 : 130 = 10:13

Let Q takes x days to do the work

Then, 10:13 :: 23:x

=> x = 23x13/10

=> x = 299/10

P's 1 day's work = 1/23

Q's 1 day's work = 10/299

(P+Q)'s 1 day's work = (1/23 + 10/299) = 23/299 = 1/13

Hence, P & Q together can complete the work in 13 days.

Report Error

View Answer Workspace Report Error Discuss

10 222
Q:

If 2 men and 3 women can do a piece of work in 8 days and 3 men and 2 women in 7 days. In how many days can the work be done by 5 men and 4 women working together?

A) 3 days B) 6 days
C) 4 days D) 2 days
 
Answer & Explanation Answer: C) 4 days

Explanation:

From the given data,

=> (2 M + 3W) 8 = (3M + 2W)7

=> 16M + 24W = 21M + 14 W

=> 10W = 5M

=> 2W = M

=> 14W × ? = 7W × 8

? = 4 days

Report Error

View Answer Workspace Report Error Discuss

11 291
Q:

28 Men and 52 women working together completes a work in 22.5 days. 35 men and 65 women working together on same work will complete it in how many days?

A) 16 B) 18
C) 19 D) 21
 
Answer & Explanation Answer: B) 18

Explanation:

clearly total persons are increased in => 28/35 :: 52/65 = 4:5

As time is inversely proportional to men, so total time will decrease in the ratio 5:4

Hence, 22.5 x 4/5 = 18 days.

Report Error

View Answer Workspace Report Error Discuss

6 156
Q:

A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left?

A) 8/15 B) 7/9
C) 6/13 D) 4/11
 
Answer & Explanation Answer: A) 8/15

Explanation:
P's 1 day's work = 1  
15
Q's 1 day's work = 1  
20
(P + Q)'s 1 day's work = ( 1 + 1 ) = 7  
15 20 60
(P + Q)'s 4 day's work = ( 7 x 4 ) = 7  
60 15
Therefore, Remaining work = ( 1 - 7 ) = 8 .
15 15
Report Error

View Answer Workspace Report Error Discuss

7 210
Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days

=> 1 day work of X = 1/10

Y can do in 15 days

=> 1 day work of Y = 1/15

1day work of (X + Y) = 1/10 + 1/15 = 1/6

Given they are hired for 5 days

=> 5 days work of (X + Y) = 5 x 1/6 = 5/6

Therefore, Unfinished work = 1 - 5/6 = 1/6 

Report Error

View Answer Workspace Report Error Discuss

8 354