9
Q:

Adam and Smith are working on a project. Adam takes 6 hrs to type 36 pages on a computer, while Smith takes 5 hrs to type 40 pages. How much time will they take, working together on two different computers to type a project of 120 pages?

A) 8 hrs 45 min B) 8 hrs 42 min
C) 8 hrs D) 8 hrs 34 min

Answer:   D) 8 hrs 34 min



Explanation:

Number of pages typed by Adam in 1 hour =  = 6
Number of pages typed by Smith in 1 hour =  = 8
Number of pages typed by both in 1 hour = (6 + 8) = 14
Time taken by both to type 110 pages = (120 * 1/14) = 8  = 8 hrs 34 min.

Q:

Pavan and Sravan are two persons. If Pavan works with his actual efficiency and Sravan twice of his actual efficiency then it takes 25 days to complete the work. But If Pavan works twice of his actual efficiency and Sravan with his normal efficiency then the work is completed in 20 days. How many days would it take if Sravan alone works with his actual efficiency (in Days)?

A) 50 B) 100
C) 70 D) 35
 
Answer & Explanation Answer: B) 100

Explanation:

Let the Efficiency of pavan be E(P)

Let the Efficiency of sravan be E(S)

Here Work W = LCM(25,20) = 100

Now, E(P+2S) = 100/25 = 4 ....(1)

E(2P+S) = 100/20 = 5 ....(2)

Hence, from (1) & (2) we get

E(S) = 1

=> Number of days Savan alone work to complete the work  = 100/1 = 100 days.

Report Error

View Answer Workspace Report Error Discuss

10 339
Q:

A contractor undertake to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged so that the work may finish in time ? 

A) 64 B) 62
C) 58 D) 56
 
Answer & Explanation Answer: D) 56

Explanation:

Days remaining 124 – 64 = 60 days

Remaining work = 1 - 2/3 = 1/3

Let men required men for working remaining days be 'm'

So men required = (120 x 64)/2 = (m x 60)/1 => m = 64

Men discharge = 120 – 64 = 56 men.

Report Error

View Answer Workspace Report Error Discuss

6 558
Q:

A can build a wall in 16 days while B can destroy it in 8 days. A worked for 5 days. Then B joined with A for the next 2 days. Find in how many days could A build the remaining wall ?

A) 12 days B) 14 days
C) 13 days D) 16 days
 
Answer & Explanation Answer: C) 13 days

Explanation:

Now, Total work = LCM(16, 8) = 48

A's one day work = + 48/16 = + 3

B's one day work = - 48/8 = -6

Given A worked for 5 days to build the wall => 5 days work = 5 x 3 = + 15

2days B joined with A in working = 2(3 - 6) = - 6

Remaining Work of building wall = 48 - (15 - 6) = 39

Now this remaining work will be done by A in = 39/3 = 13 days.

Report Error

View Answer Workspace Report Error Discuss

8 429
Q:

A mother can do a certain job in x hours. Her daughter takes twice as long to do the job. Working together, they can do the job in 6 hours. How many hours does the mother take to do the job ?

A) 3 B) 6
C) 9 D) 12
 
Answer & Explanation Answer: C) 9

Explanation:

The mother completes the job in x hours.
So, the daughter will take 2x hours to complete the same job.

 

In an hour, the mother will complete 1/x of the total job.
In an hour, the daughter will complete 1/2x of the total job.

 

So, if the mother and daughter work together, in an hour they will complete 1/x + 1/2x of the job.
i.e., in an hour they will complete 3/2x of the job.

 

The question states that they complete the entire task in 6 hours if they work together.
i.e., they complete 1/6 th of the task in an hour.

 

Equating the two information, we get 3/2x = 1/6
By solving for x, we get 2x = 18 or x = 9.

 

The mother takes 9 hours to complete the job.

Report Error

View Answer Workspace Report Error Discuss

8 504
Q:

K can lay Highway road between two cities in 16 days. L can do the same job in 12 days. With the help of M, they completes the job in 4 days. How much days does it take for M alone to complete the work ?

A) 47/7 days B) 59/6 days
C) 48/5 days D) 57/5 days
 
Answer & Explanation Answer: C) 48/5 days

Explanation:

Amount of work K can do in 1 day = 1/16

Amount of work L can do in 1 day = 1/12

Amount of work K, L and M can together do in 1 day = 1/4

Amount of work M can do in 1 day = 1/4 - (1/16 + 1/12) = 3/16 – 1/12 = 5/48

=> Hence M can do the job on 48/5 days = 9 (3/5) days  

Report Error

View Answer Workspace Report Error Discuss

6 396