9
Q:

Adam and Smith are working on a project. Adam takes 6 hrs to type 36 pages on a computer, while Smith takes 5 hrs to type 40 pages. How much time will they take, working together on two different computers to type a project of 120 pages?

A) 8 hrs 45 min B) 8 hrs 42 min
C) 8 hrs D) 8 hrs 34 min

Answer:   D) 8 hrs 34 min



Explanation:

Number of pages typed by Adam in 1 hour =  = 6
Number of pages typed by Smith in 1 hour =  = 8
Number of pages typed by both in 1 hour = (6 + 8) = 14
Time taken by both to type 110 pages = (120 * 1/14) = 8  = 8 hrs 34 min.

Q:

After working for 8 days, Hari Ram finds that only 1/3 rd of the work has been done. He employs Satya who is 60% as efficient as Hari Ram. How many days more would Satya take to complete the work ?

A) 24 1/2 days B) 25 3/2 days
C) 24 2/3 days D) 26 2/3 days
 
Answer & Explanation Answer: D) 26 2/3 days

Explanation:

1/3 ---- 8

1 -------?
Hari can do total work in = 24 days

As satya is 60% efficient as Hari, then

Satya = 1/24 x 60/100 = 1/40

=> Satya can do total work in 40 days

1 ----- 40

2/3 ---- ? => 26 2/3 days.

Report Error

View Answer Workspace Report Error Discuss

6 547
Q:

Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?

A) 4 days B) 8 days
C) 3 days D) 6 days
 
Answer & Explanation Answer: D) 6 days

Explanation:

4/10 + 9/x = 1

=> x = 15

Then both can do in

1/10 + 1/15 = 1/6

=> 6 days

Report Error

View Answer Workspace Report Error Discuss

3 436
Q:

12 men complete a work in 9 days. After they have worked for 6 days, 4 more men join them. How many days will they take to complete the remaining work ?

A) 2 days B) 2.5 days
C) 2.25 days D) 3 days
 
Answer & Explanation Answer: C) 2.25 days

Explanation:

1 man's 1 day work = 1/108
12 men's 6 day's work = 1/9 x 6 = 2/3

Remaining work = 1 - 2/3 = 1/3

16 men's 1 day work = 1/108 x 16 = 4/27
4/27 work is done by them in 1 day.

1/3 work is done by them in 27/4 x 1/3 = 9/4 days.

Report Error

View Answer Workspace Report Error Discuss

3 562
Q:

P alone can complete a piece of work in 6 days. Work done by Q alone in one day is equal to one-third of the work done by P alone in one day. In how many days can the work be completed if P and Q work together  ?

A) 5 (2/3) B) 6 (3/4 )
C) 4 (1/2) D) 3
 
Answer & Explanation Answer: C) 4 (1/2)

Explanation:

Work done by P alone in one day = 1/6th of the total work done by Q alone in one day = 1/3(of that done by P in one day) = 1/3(1/6 of the total) = 1/18 of the total.

Work done by P and Q, working together in one day = 1/6 + 1/18  = 4/18 = 2/9 of the total
 
They would take 9/2 days = 4 (1/2) days to complete the work working together.
Report Error

View Answer Workspace Report Error Discuss

2 395
Q:

A can do a piece of work in 30 days. He works at it for 6 days and then B finishes it in 18 days. In what time can A and B together it ?

A) 14 1/2 days B) 11 days
C) 13 1/4 days D) 12 6/7 days
 
Answer & Explanation Answer: D) 12 6/7 days

Explanation:

Let 'B' alone can do the work in 'x' days

6/30 + 18/x = 1
x = 22.5
1/30 + 1/22.5 = 7/90

=> 90/7 = 12 6/7 days

Report Error

View Answer Workspace Report Error Discuss

6 722