9
Q:

Adam and Smith are working on a project. Adam takes 6 hrs to type 36 pages on a computer, while Smith takes 5 hrs to type 40 pages. How much time will they take, working together on two different computers to type a project of 120 pages?

A) 8 hrs 45 min B) 8 hrs 42 min
C) 8 hrs D) 8 hrs 34 min

Answer:   D) 8 hrs 34 min



Explanation:

Number of pages typed by Adam in 1 hour =  = 6
Number of pages typed by Smith in 1 hour =  = 8
Number of pages typed by both in 1 hour = (6 + 8) = 14
Time taken by both to type 110 pages = (120 * 1/14) = 8  = 8 hrs 34 min.

Q:

P can do a piece of work in 5 less days than Q. If both of them can do the same work in  days, in how many days will Q alone do the same work  ?

A) 24 days B) 25 days
C) 20 days D) 19 days
 
Answer & Explanation Answer: B) 25 days

Explanation:

Let Q complete that work in 'L' days

=>

=>

L = 25 days.

Report Error

View Answer Workspace Report Error Discuss

8 409
Q:

Time taken by P alone to finish a work is 50% more than the time taken by P and Q together. Q is thrice as efficient as R. If Q and R together can complete the work in 22.5 days, then how many days will P alone take to complete the work ?

A) 17 days B) 11 days
C) 15 days D) 16 days
 
Answer & Explanation Answer: C) 15 days

Explanation:

We know that Time is inversely proportional to Efficiency

Here given time ratio of P & P+Q as

P/P+Q = 150/100 = 3:2

Efficiency ratio of P & Q as

P:Q = 2:1 ....(1)

Given Efficiency ratio of Q & R as

Q:R = 3:1 ....(2)

From (1) & (2), we get

P:Q:R = 6:3:1

P alone can finish the work in

22.5(3+1)/6 = 15 days.

Report Error

View Answer Workspace Report Error Discuss

5 640
Q:

A town having teenagers(boys & girls) of 5000 requires 150 litre of water per head. It has a tank measuring 20 m × 15 m × 5 m. The water of this tank will sufficient for ____ days.

A) 8 B) 6
C) 4 D) 2
 
Answer & Explanation Answer: D) 2

Explanation:

Total Water reqduired = 5000 × 150 lit

= 750,000 litres = 750 cu.m.

Volume of tank = 20 × 15 × 5 = 1500 Cu.m.

Number of days required =1500/750 = 2 days.

Report Error

View Answer Workspace Report Error Discuss

6 341
Q:

Priya can do a work in 16 days. In how many days will the work be completed by Sai, if the efficiency of Sai is 60% more than that of Priya ?

A) 8 days B) 12 days
C) 14 days D) 10 days
 
Answer & Explanation Answer: D) 10 days

Explanation:

Ratio of efficiencies of Priya and Sai is

Sai : Priya = 160 : 100 = 8 : 5

Given Priya completes the work in 16 days

Let number of days Sai completes the work be 'd'

=> 5×16 = 8×d

d = 10 days.

Therefore, number of days Sai completes the work is 10 days.

Report Error

View Answer Workspace Report Error Discuss

9 516
Q:

Pavan and Sravan are two persons. If Pavan works with his actual efficiency and Sravan twice of his actual efficiency then it takes 25 days to complete the work. But If Pavan works twice of his actual efficiency and Sravan with his normal efficiency then the work is completed in 20 days. How many days would it take if Sravan alone works with his actual efficiency (in Days)?

A) 50 B) 100
C) 70 D) 35
 
Answer & Explanation Answer: B) 100

Explanation:

Let the Efficiency of pavan be E(P)

Let the Efficiency of sravan be E(S)

Here Work W = LCM(25,20) = 100

Now, E(P+2S) = 100/25 = 4 ....(1)

E(2P+S) = 100/20 = 5 ....(2)

Hence, from (1) & (2) we get

E(S) = 1

=> Number of days Savan alone work to complete the work  = 100/1 = 100 days.

Report Error

View Answer Workspace Report Error Discuss

10 489