Four pipes A,B, C and D can fill a cistern  in 20,25, 40 and 50 hours respectively.The first pipe A was opened at 6:00 am, B at 8:00 am, C at 9:00 am and D at 10:00 am. when will the Cistern be full?

A) 4:18 pm B) 3:09 pm
C) 12:15 pm D) 11:09 am

Answer:   B) 3:09 pm



Explanation:

Efficiency of P= 5%

Efficiency of Q= 4%

Efficiency of R= 2.5%

Efficiency of S= 2%

\inline \left.\begin{matrix} Till \; 10\: am \; pipe\; P \; filled\; 20\; percent\\ Till \; 10\: am \; pipe\; Q \; filled\; 8\; percent\\ Till \; 10\: am \; pipe\; R \; filled\; 2.5\; percent \end{matrix}\right\}30.5 %

Thus, at 10 am pipe P,Q and R filled 30.5% of the cistern.

Now, the time taken by P,Q,R and S together to fill the remaining capacity of the cistern

       =\inline \frac{69.5}{13.5} = \inline \frac{139}{27} =5 Hours and 9 minutes(approx)

Therefore, total time =4 hrs + 5hrs 9 mins

                              = 9 hrs and 9 mins

It means cistern will be filled up at 3:09 pm

Q:

A mother can do a certain job in x hours. Her daughter takes twice as long to do the job. Working together, they can do the job in 6 hours. How many hours does the mother take to do the job ?

A) 3 B) 6
C) 9 D) 12
 
Answer & Explanation Answer: C) 9

Explanation:

The mother completes the job in x hours.
So, the daughter will take 2x hours to complete the same job.

 

In an hour, the mother will complete 1/x of the total job.
In an hour, the daughter will complete 1/2x of the total job.

 

So, if the mother and daughter work together, in an hour they will complete 1/x + 1/2x of the job.
i.e., in an hour they will complete 3/2x of the job.

 

The question states that they complete the entire task in 6 hours if they work together.
i.e., they complete 1/6 th of the task in an hour.

 

Equating the two information, we get 3/2x = 1/6
By solving for x, we get 2x = 18 or x = 9.

 

The mother takes 9 hours to complete the job.

Report Error

View Answer Workspace Report Error Discuss

4 75
Q:

K can lay Highway road between two cities in 16 days. L can do the same job in 12 days. With the help of M, they completes the job in 4 days. How much days does it take for M alone to complete the work ?

A) 47/7 days B) 59/6 days
C) 48/5 days D) 57/5 days
 
Answer & Explanation Answer: C) 48/5 days

Explanation:

Amount of work K can do in 1 day = 1/16

Amount of work L can do in 1 day = 1/12

Amount of work K, L and M can together do in 1 day = 1/4

Amount of work M can do in 1 day = 1/4 - (1/16 + 1/12) = 3/16 – 1/12 = 5/48

=> Hence M can do the job on 48/5 days = 9 (3/5) days  

Report Error

View Answer Workspace Report Error Discuss

5 68
Q:

After working for 8 days, Hari Ram finds that only 1/3 rd of the work has been done. He employs Satya who is 60% as efficient as Hari Ram. How many days more would Satya take to complete the work ?

A) 24 1/2 days B) 25 3/2 days
C) 24 2/3 days D) 26 2/3 days
 
Answer & Explanation Answer: D) 26 2/3 days

Explanation:

1/3 ---- 8

1 -------?
Hari can do total work in = 24 days

As satya is 60% efficient as Hari, then

Satya = 1/24 x 60/100 = 1/40

=> Satya can do total work in 40 days

1 ----- 40

2/3 ---- ? => 26 2/3 days.

Report Error

View Answer Workspace Report Error Discuss

6 185
Q:

Amar can do a piece of work in 10 days. He works at it for 4 days and then Arun finishes it in 9 days. In how many days can Amar and Arun together finish the work ?

A) 4 days B) 8 days
C) 3 days D) 6 days
 
Answer & Explanation Answer: D) 6 days

Explanation:

4/10 + 9/x = 1

=> x = 15

Then both can do in

1/10 + 1/15 = 1/6

=> 6 days

Report Error

View Answer Workspace Report Error Discuss

3 147
Q:

12 men complete a work in 9 days. After they have worked for 6 days, 4 more men join them. How many days will they take to complete the remaining work ?

A) 2 days B) 2.5 days
C) 2.25 days D) 3 days
 
Answer & Explanation Answer: C) 2.25 days

Explanation:

1 man's 1 day work = 1/108
12 men's 6 day's work = 1/9 x 6 = 2/3

Remaining work = 1 - 2/3 = 1/3

16 men's 1 day work = 1/108 x 16 = 4/27
4/27 work is done by them in 1 day.

1/3 work is done by them in 27/4 x 1/3 = 9/4 days.