10
Q:

There are three boats B1, B2 and B3 working together they carry 60 people in each trip. One day an early morning B1 carried 50 people in few trips alone. When it stopped carrying the passengers B2 and B3 started carrying the people together. It took a total of 10 trips to carry 300 people by B1, B2 and B3. It is known that each day on an average 300 people cross the river using only one of the 3 boats B1, B2 and B3. How many trips it would take to B1, to carry 150 passengers alone?

A) 15 B) 30
C) 25 D) 10

Answer:   A) 15

Explanation:

Combined efficiency of all the three boats = 60 passenger/trip

Now, consider option(a)

15 trips and 150 passengers means efficiency  of B1 =  

which means in carrying 50 passengers B1 must has taken 5 trips. So the rest trips equal to 5 (10-5 = 5) in which B2 and B3 together carried remaining 250 (300 - 50 = 250) Passengers.

Therefore the efficiency of B2 and B3 = 

Since, the combined efficiency of B1, B2 and B3 is 60. Which is same as given in the first statement hence option(a) is correct.

Q:

A take twice as much time as B or thrice as much time to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in  ?

A) 8 hrs B) 12 hrs
C) 6 hrs D) 4 hrs
 
Answer & Explanation Answer: C) 6 hrs

Explanation:

Suppose A, B and C take x, x/2 and x/3 respectively to finish the work. 

Then, (1/x + 2/x + 3/x) = 1/2 
 
6/x = 1/2 => x = 12 
 
So, B takes 6 hours to finish the work.
Report Error

View Answer Workspace Report Error Discuss

1 6
Q:

Sixty men can stitch 150 shirts in 30 days working 8 hours a day. In how many days can 35 men stitch 200 shirts working 6 hours a day ?

A) 87.5 B) 89
C) 91.5 D) 93.5
 
Answer & Explanation Answer: C) 91.5

Explanation:

We have M1 D1 H1 / W1 = M2 D2 H2 / W2 (Variation rule)
(60 x 30 x 8)/ 150 = (35 x D2 x 6) / 200
D2 = (60 x 30 x 8 x 200) / (150 x 35 x 6) => D2 = 91.42 days =~ 91.5 days.

Report Error

View Answer Workspace Report Error Discuss

1 33
Q:

A can complete a piece of work in 12 days and B is 60% more efficient than A. In how many days B will complete the same work  ?

A) 8.7 hrs B) 5.2 hrs
C) 5 hrs D) 7.5 hrs
 
Answer & Explanation Answer: D) 7.5 hrs

Explanation:

Ratio of times taken by A and B = 160 : 100
A can do the work in 12 days
Let B can do the work in "D" days
=> 160:100 = 12 : D
=> D = 12 x 100/160 = 7.5 hrs

Report Error

View Answer Workspace Report Error Discuss

2 50
Q:

A can finish a work in 18 days and B can do the same work in half the time taken by A. then, working together, what part of the same work they can finish in a day ?

A) Total work B) One-fourth work
C) Half work D) Two-third work
 
Answer & Explanation Answer: C) Half work

Explanation:

A can do the work = 18 days
B can do the work = 18/2 = 9 days
(A + B)'s 1 day work = 1/18 + 1/9 = 1/6
=> In 3 days = 3x1/6 = 1/2 work is completed.

Report Error

View Answer Workspace Report Error Discuss

1 36
Q:

10 boys can complete a work in 7 days and 10 girls take 14 days to complete the work. How many days will 5 boys and 10 girls take to complete the work ?

A) 13 days B) 10 days
C) 7 days D) 16 days
 
Answer & Explanation Answer: C) 7 days

Explanation:

1 boy's 1 day work = 1/70
1 girl's 1 day work = 1/140
(5 boys + 10 girls)'s 1 day work
= (5/70 + 10/140) = (1/14 + 1/14) = 1/7

5 boys and 10 girls will complete the work in 7 days.

Report Error

View Answer Workspace Report Error Discuss

2 50