8
Q:

There are three boats B1, B2 and B3 working together they carry 60 people in each trip. One day an early morning B1 carried 50 people in few trips alone. When it stopped carrying the passengers B2 and B3 started carrying the people together. It took a total of 10 trips to carry 300 people by B1, B2 and B3. It is known that each day on an average 300 people cross the river using only one of the 3 boats B1, B2 and B3. How many trips it would take to B1, to carry 150 passengers alone?

A) 15 B) 30
C) 25 D) 10

Answer:   A) 15

Explanation:

Combined efficiency of all the three boats = 60 passenger/trip

Now, consider option(a)

15 trips and 150 passengers means efficiency  of B1 =  

which means in carrying 50 passengers B1 must has taken 5 trips. So the rest trips equal to 5 (10-5 = 5) in which B2 and B3 together carried remaining 250 (300 - 50 = 250) Passengers.

Therefore the efficiency of B2 and B3 = 

Since, the combined efficiency of B1, B2 and B3 is 60. Which is same as given in the first statement hence option(a) is correct.

Q:

A can do a work in 9 days, B can do a work in 7 days, C can do a work in 5 days. A works on the first day, B works on the second day and C on the third day respectively that is they work on alternate days. When will they finish the work ?

A) [7 + (215/345)] days B) [6 + (11/215)] days
C) [6 + (261/315)] days D) [5 + (112/351)] days
 
Answer & Explanation Answer: C) [6 + (261/315)] days

Explanation:

After day 1, A finishes 1/9 of the work.

After day 2, B finishes 1/7 more of the total work. (1/9) + (1/7) is finished.

After day 3, C finishes 1/5 more of total work. Total finished is 143/315.

So, after day 6, total work finished is 286/315.

Now remaining work = 315 - 286 = 29 /315

On day 7, A will work again

Work will be completed on day 7 when A is working. He must finish 29/315 of total remaining work.

Since he takes 9 days to finish the total task, he will need 261/315 of the day.

Total days required is 6 + (261/315) days.

Report Error

View Answer Workspace Report Error Discuss

2 20
Q:

One girl can eat 112 chocolates in half a minute, and her boy friend can eat half as many in twice the length of time. How many chocolates can both boy and girl eat in 12 seconds ?

A) 44 B) 32
C) 56 D) 49
 
Answer & Explanation Answer: C) 56

Explanation:

Girl eats 112 chocolates in 30 sec
so she can eat in 12 sec is 12 x 112/30 = 44.8 chocolates.

Her boy friend can eat one-half of 112 in twice of 30 sec
so he can eat 56 in 60 sec
Then he can eat in 12 sec is 56 x 12/60 = 11.2 chocolates.

Hence, together they can eat
=> 44.8 + 11.2
56 chocolates in 12 seconds.

Report Error

View Answer Workspace Report Error Discuss

5 12
Q:

Two boys and a girl can do a work in 5 days, while a boy and 2 girls can do it in 6 days. If the boy is paid at the rate of 28$ a week, what should be the wages of the girl a week ?

A) 24 $ B) 22 $
C) 16 $ D) 14 $
 
Answer & Explanation Answer: C) 16 $

Explanation:

Let the 1 day work of a boy=b and a girl=g, then
2b + g = 1/5 ---(i) and
b + 2g = 1/6 ---(ii)
On solving (i) & (ii), b=7/90, g=2/45
As payment of work will be in proportion to capacity of work and a boy is paid $ 28/week,
so a girl will be paid 28x  = 16 $.

Report Error

View Answer Workspace Report Error Discuss

3 11
Q:

A constructor estimates that 4 people can paint Mr. Karthik's house in 6 days. If he uses 5 people instead of 4, how long will they take to complete the job ?

A) 3 days B) 26/3 days
C) 13/4 days D) 24/5 days
 
Answer & Explanation Answer: D) 24/5 days

Explanation:

we know that m1 x d1 = m2 x d2
=> 4 x 6 = 5 x d
where d = no. of days taken by 5 men to paint
d = 24/5 days.

Report Error

View Answer Workspace Report Error Discuss

4 17
Q:

6 boys and 8 girls can do job in 10 days , 26 boys & 48 women do work in 2 days. Find time taken by 15 boys and 20 girls to do same work ?

A) 2 days B) 3 days
C) 4 days D) 5 days
 
Answer & Explanation Answer: C) 4 days

Explanation:

One day work of 6 boys and 8 girls is given as 6b + 8g = 1/10 -------->(I)
One day work of 26 boys and 48 women is given as 26b + 48w = 1/2 -------->(II)

Divide both sides by 2 in (I) and then multiply both sides by 5
Now we get
15b + 20g = 1/4.
Therefore, 15 boys and 20 girls can do the same work in 4 days.

Report Error

View Answer Workspace Report Error Discuss

5 16