Quantitative Aptitude - Arithmetic Ability Questions


What is Quantitative Aptitude - Arithmetic Ability?

 

Quantitative Aptitude - Arithmetic Ability test helps measure one's numerical ability, problem solving and mathematical skills. Quantitative aptitude - arithmetic ability is found in almost all the entrance exams, competitive exams and placement exams. Quantitative aptitude questions includes questions ranging from pure numeric calculations to critical arithmetic reasoning. Questions on graph and table reading, percentage analysis, categorization, simple interests and compound interests, clocks, calendars, Areas and volumes, permutations and combinations, logarithms, numbers, percentages, partnerships, odd series, problems on ages, profit and loss, ratio & proportions, stocks &shares, time & distance, time & work and more .

 

Every aspirant giving Quantitative Aptitude Aptitude test tries to solve maximum number of problems with maximum accuracy and speed. In order to solve maximum problems in time one should be thorough with formulas, theorems, squares and cubes, tables and many short cut techniques and most important is to practice as many problems as possible to find yourself some tips and tricks in solving quantitative aptitude - arithmetic ability questions.

 

Wide range of Quantitative Aptitude - Arithmetic Ability questions given here are useful for all kinds of competitive exams like Common Aptitude Test(CAT), MAT, GMAT, IBPS and all bank competitive exams, CSAT, CLAT, SSC Exams, ICET, UPSC, SNAP Test, KPSC, XAT, GRE, Defence, LIC/G IC, Railway exams,TNPSC, University Grants Commission (UGC), Career Aptitude test (IT companies), Government Exams and etc.


Q:

A clock is set right at 8 a.m. The clock gains 10 minutes in 24 hours will be the true time when the clock indicates 1 p.m. on the following day?

A) 48 min. past 12. B) 46 min. past 12.
C) 45 min. past 12. D) 47 min. past 12.
 
Answer & Explanation Answer: A) 48 min. past 12.

Explanation:

Time from 8 a.m. on a day to 1 p.m. on the following day = 29 hours. 

24 hours 10 min. of this clock = 24 hours of the correct clock. 

1456 hrs of this clock = 24 hours of the correct clock. 

29 hours of this clock = 24*6145*29 hrs of the correct clock 

= 28 hrs 48 min of the correct clock. 

Therefore, the correct time is 28 hrs 48 min. after 8 a.m. 

This is 48 min. past 12.

Report Error

View Answer Report Error Discuss

846 193901
Q:

If 20% of a = b, then b% of 20 is the same as :

A) 4% of a B) 6% of a
C) 8% of a D) 10% of a
 
Answer & Explanation Answer: A) 4% of a

Explanation:

20% of a = b 

=> (20/100) * a = b 

 b% of 20 =(b/100) x 20 = [(20a/100)  / 100] x 20= 4a/100 = 4% of a.

Report Error

View Answer Report Error Discuss

1498 189203
Q:

Insert the missing number.

16, 33, 65, 131, 261, (....)

A) 523 B) 521
C) 613 D) 721
 
Answer & Explanation Answer: A) 523

Explanation:

Each number is twice the preceding one with 1 added or subtracted alternatively.

So, the next number is (2 x 261 + 1) = 523.

Report Error

View Answer Report Error Discuss

60 188915
Q:

What is the next number in the given Number Series?

5, 24, 94, 279, ?

A) 587 B) 554
C) 489 D) 499
 
Answer & Explanation Answer: B) 554

Explanation:

The given number series follows a pattern that

5 x 5 – 1 = 24

24 x 4 – 2 = 94

94 x 3 – 3 = 279

279 x 2 – 4 = 554

Report Error

View Answer Report Error Discuss

22 188536
Q:

Find out the wrong number in the given sequence of numbers.

56, 72, 90, 110, 132, 150

A) 72 B) 110
C) 132 D) 150
 
Answer & Explanation Answer: D) 150

Explanation:

The numbers are 7 x 8, 8 x 9, 9 x 10, 10 x 11, 11 x 12, 12 x 13.

So, 150 is wrong.

Report Error

View Answer Report Error Discuss

22 187976
Q:

A, B and C can do a piece of work in 24 days, 30 days and 40 days respectively. They began the work together but C left 4 days before the completion of the work. In how many days was the work completed?

A) 11 days B) 12 days
C) 13 days D) 14 days
 
Answer & Explanation Answer: A) 11 days

Explanation:

One day's work of A, B and C = (1/24 + 1/30 + 1/40) = 1/10.

C leaves 4 days before completion of the work, which means only A and B work during the last 4 days.

Work done by A and B together in the last 4 days = 4 (1/24 + 1/30) = 3/10.

Remaining Work = 7/10, which was done by A,B and C in the initial number of days. 

Number of days required for this initial work = 7 days. 

Thus, the total numbers of days required = 4 + 7 = 11 days.

Report Error

View Answer Report Error Discuss

666 186488
Q:

8 litres are drawn from a cask full of wine and is then filled with water. This operation is performed three more times. The ratio of the quantity of wine now left in cask to that of the water is 16 : 65. How much wine the cask hold originally?

A) 18 litres B) 24 litres
C) 32 litres D) 42 litres
 
Answer & Explanation Answer: B) 24 litres

Explanation:

Let the quantity of the wine in the cask originally be x litres

 
Then, quantity of wine left in cask after 4 operations =x1-8x4litres

 

x1-8x4x = 1681  

 

 1-8x4=234 

 

x=24

Report Error

View Answer Report Error Discuss

685 183433
Q:

Find the odd number out of the following number series?

2 4 8 11.5 18.25 28.375

A) 18.25 B) 28.375
C) 11.5 D) 8
 
Answer & Explanation Answer: D) 8

Explanation:

Given number series follows a pattern that,

2

2 x 1.5 + 1 = 4

4 x 1.5 + 1 = 7 (not equal to 8)

7 x 1.5 + 1 = 11.5

11.5 x 1.5 + 1 = 18.25

18.25 x 1.5 + 1 = 28.375

 

Hence, the odd number in the given number series is 8.

Report Error

View Answer Report Error Discuss

17 181011