FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Sashi can do a piece of work in 20 days. Tanya is 25% more efficient than Sashi. The number of days taken by Tanya to do the same piece of work is:

A) 15 B) 16
C) 18 D) 25
 
Answer & Explanation Answer: B) 16

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 2022
Q:

35 persons are engaged to complete a work in 60 days. After 32 days it is observed that only (2/5)th part of the work has been done. The number of persons to be engaged to complete the remaining work in the said period is

A) 20 B) 35
C) 30 D) 25
 
Answer & Explanation Answer: D) 25

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2020
Q:

Pramod can paint a wall red in 12 hours while Brajen can whitewash the wall completely in 16 hrs. If Pramod and Brajen work alternately for an hour each starting when the wall has just cement on it till when it is completely painted red, how many hours will it take to paint the entire wall red?

 

A) 89 B) 96
C) 48 D) 95
 
Answer & Explanation Answer: A) 89

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 2014
Q:

Prahlad has done 1/3rd of a job in 30 days, Sarfaraz completes the rest of the job in 90 days. In how many days can they together do the job?

A) 27 days B) 18 days
C) 54 days D) 36 days
 
Answer & Explanation Answer: C) 54 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1998
Q:

Makarand works 2 times as fast as Samarjit. If Samarjit can complete a job alone in 27 days, then in how many days can they together finish the job?

A) 6 days B) 7 days
C) 5 days D) 9 days
 
Answer & Explanation Answer: D) 9 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1998
Q:

A can do 75% of a job in 9 days and B can do half of the job in 8 days. If they work on it together, then in how many days can they do half of the job?

A) 40/7 B) 24/7
C) 7/2 D) 9/2
 
Answer & Explanation Answer: B) 24/7

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1996
Q:

A can do a work in 36 days and B in 12 days. If they work on it together for 3 days, then what fraction of work is left?

A) 2/3 B) 1/3
C) 1/4 D) 1/5
 
Answer & Explanation Answer: A) 2/3

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1989
Q:

A can complete a task alone in 8 days, while B takes 12 days to do it by herself. Together with C it takes them 4 days to complete the work. If C and D together can complete the task in 15 days, then how many days will D need to complete the task by herself?

A) 36 B) 32
C) 40 D) 30
 
Answer & Explanation Answer: C) 40

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1984