Q:

In the following question, four number pairs are given. The number on left side of (–) is related to the number on the right side of (–) with some Logic/Rule/Relation. Three are similar on basis of same Logic/Rule/Relation. Select the odd one out from the

A) 15 – 45 B) 11 – 33
C) 15 – 55 D) 19 – 57
 
Answer & Explanation Answer: C) 15 – 55

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

0 1512
Q:

What is the slope of the line perpendicular to the line passing through the points (-2, 3) and (2, 0)?

A) 4/3 B) 3/4
C) -3/4 D) -4/3
 
Answer & Explanation Answer: A) 4/3

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1512
Q:

26% of a number is 65. What is the number?

A) 50 B) 250
C) 260 D) 40
 
Answer & Explanation Answer: B) 250

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

2 1512
Q:

If x + 1x = -2, then the value of x631 + 1x632?

A) -2 B) -1
C) 0 D) 2
 
Answer & Explanation Answer: C) 0

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 1511
Q:

A thief is stopped by a policeman from a distance of 350 metres. When the policeman starts the chase, the thief also starts running. Assuming the speed of the thief as 7 km/h and that of police man as 12 km/h, how far the thief would have run, before he is over taken?

A) 490 metres B) 392 metres
C) 588 metres D) 294 metres
 
Answer & Explanation Answer: A) 490 metres

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: Bank Exams

0 1511
Q:

If 1+y16-74, then the value of 5y-15

A) 110 B) 130
C) 150 D) 160
 
Answer & Explanation Answer: C) 150

Explanation:
Report Error

View Answer Report Error Discuss

0 1511
Q:

A, B and C can complete a work in 20, 24 and 30 days respectively. All three of them starts together but after 4 days A leaves the job and B left the job 6days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?

A) 10 B) 12
C) 14 D) 16
 
Answer & Explanation Answer: C) 14

Explanation:
Report Error

View Answer Report Error Discuss

0 1511
Q:

How much does one need to add to 2/3 to obtain 3/2?

A) 5/6 B) 1.5/6
C) 1/-1 D) 4/9
 
Answer & Explanation Answer: C) 1/-1

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Decimal Fractions
Exam Prep: Bank Exams

2 1511