Q:

The area of a square is 72.25 cm². Find its perimeter (in cm).

A) 68 B) 44
C) 34 D) 88
 
Answer & Explanation Answer: C) 34

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

0 1829
Q:

In a triangle, the distance of the centroid from the three vertices is 4cm, 6cm and 8cm respectively. Then the length of the smallest median is:

A) 8 B) 7
C) 6 D) 5
 
Answer & Explanation Answer: C) 6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

0 1828
Q:

The original price of a TV set is Rs. 6,000. If the price is discounted by 20% and then raised by 10% for service contract, the price charged by the shopkeeper is

A) Rs. 5400 B) Rs. 5280
C) Rs. 5100 D) Rs. 4200
 
Answer & Explanation Answer: B) Rs. 5280

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

2 1828
Q:

The average weight of 10 parcels is 1.7 kg. Addition of another new parcel reduces the average weight by 60 gram. What is the weight , in kg, of the new parcel?

A) 1.04 B) 1.08
C) 1.4 D) 1.8
 
Answer & Explanation Answer: A) 1.04

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Average
Exam Prep: Bank Exams

2 1828
Q:

What is the average of all numbers between 9 and 90 which are divisible by 8?

A) 53 B) 52
C) 51 D) 50
 
Answer & Explanation Answer: B) 52

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Average
Exam Prep: Bank Exams

1 1827
Q:

To travel 660 km, an Express train takes 10 hours more than Rajdhani. If however, the speed of the Express train is doubled, it takes 7 hours less than Rajdhani. The speed of Rajdhani is

A) 38.8 km/hr B) 16.2 km/hr
C) 50.1 km/hr D) 27.5 km/hr
 
Answer & Explanation Answer: D) 27.5 km/hr

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Problems on Trains
Exam Prep: Bank Exams

5 1827
Q:

On selling 25 shirts, a retailer earns profit equal to the cost price of 8 shirts. What is the profit percentage?

A) 47.05 B) 32
C) 25 D) 34.5
 
Answer & Explanation Answer: B) 32

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Profit and Loss
Exam Prep: Bank Exams

3 1827
Q:

The labourers A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days. A and C together can do it in 12 day, while A and B together can do it in 13 1/3 days. The money will be divided in the ratio

A) 4:5:6 B) 4:7:5
C) 5:7:4 D) 5:6:8
 
Answer & Explanation Answer: A) 4:5:6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1827