Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

X, Y and Z can do a piece of work in 30, 40 and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

A) 660/47 B) 640/47
C) 680/47 D) 665/47
 
Answer & Explanation Answer: A) 660/47

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1955
Q:

Surya works 3 times as fast as Ramya and is able to complete a work in 40 days less than the number of days taken by Ramya. Find the time in which they can complete the work together.

A) 20 days B) 15 days
C) 25 days D) 30 days
 
Answer & Explanation Answer: B) 15 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1953
Q:

A can do a work in 20 days and B in 10 days. If they work on it together for 5 days, then what fraction of work is left.

A) 4/9 B) 1/4
C) 1/5 D) 2/9
 
Answer & Explanation Answer: B) 1/4

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1951
Q:

A canal of a village can be cleaned by 24 villagers in 12 days. The number of days in which 36 villagers can clean the canal is ?

A) 18 B) 8
C) 72 D) 16
 
Answer & Explanation Answer: B) 8

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1951
Q:

The labourers A, B, C were given a contract of Rs. 750 for doing a certain piece of work. All the three together can finish the work in 8 days. A and C together can do it in 12 day, while A and B together can do it in 13 1/3 days. The money will be divided in the ratio

A) 4:5:6 B) 4:7:5
C) 5:7:4 D) 5:6:8
 
Answer & Explanation Answer: A) 4:5:6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1932
Q:

A does 1/2 as much work as B and C does1/2as much work as A and B together. If C alone can finish the work in 40 days, then together all will finish the work in

A) 30 days B) 40/3 days
C) 15 days D) 16 days
 
Answer & Explanation Answer: B) 40/3 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1930
Q:

A and B together do a job in 12 days and A could do the job in 20 days if he worked alone. How many days would B take to do the job if he worked alone?

A) 30 B) 25
C) 24 D) 15
 
Answer & Explanation Answer: A) 30

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1930
Q:

Smita can finish a work in 12 days and Sam can finish the same work in 9 days. After working together for 4 days they both leave the job. What is the fraction of unfinished work?

A) 2/9 B) 1/4
C) 1/2 D) 7/9
 
Answer & Explanation Answer: A) 2/9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1923