Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Arun and Amit can do a piece of work in 9 days and 12 days respectively. If they work for alternate days and Amit starts the work first, then in how many days 35/36 parts of whole work will be completed?

A) 10 days B) 12 days
C) 5 days D) 8 days
 
Answer & Explanation Answer: A) 10 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

6 1733
Q:

A can complete a work in 20 days and B can complete the same work in 25 days. If both of them work together, then in 3 days what percent of the total work will be completed?

A) 9 B) 12
C) 25 D) 27
 
Answer & Explanation Answer: D) 27

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 1729
Q:

A can do a work in 12 days and B in 24 days. If they work on it together for 4 days, then what fraction of work is left?

A) 1/3 B) 1/2
C) 1/4 D) 1/5
 
Answer & Explanation Answer: B) 1/2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1729
Q:

24 men can do a piece of work in 17 days.How many men will be able to do it in 51 days ?

A) 8 B) 10
C) 12 D) 6
 
Answer & Explanation Answer: A) 8

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1723
Q:

Raja and Kundan together can build a wall in 20 days, Kundan and Mahesh build the same wall in 30 days and Mahesh and Raja can build the same wall in 24 days. In how many days can all the three complete the same wall while working together?

A) 18 B) 16
C) 20 D) 14
 
Answer & Explanation Answer: B) 16

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 1722
Q:

If Mr. Raghav taught a total of 500 hours, then what is the difference in number of hours of teaching algebra and modern Maths?

A) 15 B) 20
C) 25 D) 40
 
Answer & Explanation Answer: C) 25

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 1719
Q:

Anil can do a piece of work in 14 days which Rohit can do in 21 days. They worked together for few days after which Anil left. If Rohit worked alone for 3 days, find the total number of days it took to complete the whole work.

A) 31/5 B) 51/5
C) 21/5 D) 13/5
 
Answer & Explanation Answer: B) 51/5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1715
Q:

An hour-long test has 60 problems. If a student completes 30 problems in 25 minutes, then the required seconds he has taken on average for computing each of the remaining problems is

A) 70 seconds B) 50 seconds
C) 40 seconds D) 30 seconds
 
Answer & Explanation Answer: A) 70 seconds

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 1707