Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

A can finish a work in 18 days and B in 36 days. If they work on it together for 9 days, then what percent of work is left?

A) 33.3 B) 20
C) 75 D) 25
 
Answer & Explanation Answer: D) 25

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

6 2829
Q:

Type 1 workers are 2.5 times as efficient as type 2 workers. Twelve Type 1 workers can complete a task in 10 days. How many days would it have taken 4 Type 1 and 15 Type 2 workers to do the same work?

 

A) 13 B) 10
C) 12 D) 11
 
Answer & Explanation Answer: D) 11

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

5 2829
Q:

P can do a work in 10 days. Q can do the same work in 15 days. If they work together for 5 days, how much of the work will they complete?

A) 1/2 B) 2/3
C) 1/3 D) 5/6
 
Answer & Explanation Answer: D) 5/6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 2822
Q:

Murad can do a piece of work in 33 hours. If he is joined by Joel who is 100% more efficient, in what time will they together finish the work?

A) 4 hours B) 6 hours
C) 2 hours D) 11 hours
 
Answer & Explanation Answer: D) 11 hours

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2819
Q:

3 men or 4 women can complete a job in 120 days. 12 men and 16 women will complete the same job in how many days?

A) 12 B) 14
C) 15 D) 18
 
Answer & Explanation Answer: C) 15

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2807
Q:

Painter A can paint a house in 40 days and Painter B can do it in 60 days. With help of C, they did the job in 20 days only. Then, C alone can do the job in

A) 120 days B) 100 days
C) 90 days D) 80 days
 
Answer & Explanation Answer: A) 120 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2776
Q:

50 men can complete a work in 28 days. They started the work together, but at the end of each 10th day, 10 men left the job. The work was completed in how many days?

A) 36 B) 38
C) 40 D) 45
 
Answer & Explanation Answer: C) 40

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , Bank Exams
Job Role: Bank PO , Bank Clerk

3 2748
Q:

45 men or 60 boys can do a piece of work in 20 days. How many days will 15 men and 20 boys take to complete the work?

A) 23 B) 45
C) 30 D) 25
 
Answer & Explanation Answer: C) 30

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2741