Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Sister can bake 50 cakes in 25 hours, Sister and Mummy together can bake 75 cakes in 15 hours. How many cakes Mummy can bake in 15 hours?

A) 25 B) 45
C) 20 D) 10
 
Answer & Explanation Answer: B) 45

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2377
Q:

A can paint a house in 25 days and B can do it in 10 days. Along with C, they did the job in 6.25 days only. Then in how many days, C alone can do the job?

A) 50 B) 40
C) 30 D) 60
 
Answer & Explanation Answer: A) 50

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

4 2373
Q:

A, B and C can complete the work in 4, 5 and 6 hours respectively. If they all work together and receive Rs. 777 as wages then find the share of A.

A) Rs. 300 B) Rs. 315
C) Rs. 326 D) Rs. 175
 
Answer & Explanation Answer: B) Rs. 315

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

10 2372
Q:

A can finish a work in 7 days . B can finish the same work in 9 days . The days required to finish the work by both of them together.

A) 31/16 B) 47/16
C) 63/16 D) 79/16
 
Answer & Explanation Answer: C) 63/16

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2368
Q:

Working alone A can do the task in 27 hours and B can do it in 54 hours. Find C's share (in Rs) if A, B and C get paid Rs 4,320 for completing a task in 12 hours on which they worked together.

A) 1440 B) 960
C) 1920 D) 1280
 
Answer & Explanation Answer: A) 1440

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2363
Q:

8 men can complete a work in 16 days. 16 women can complete the same work in 24 days. In how many days can 4 men and 8 women complete the same work?

A) B)
C) D)
 
Answer & Explanation Answer:

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

10 2354
Q:

Ram and Hari can cut 12 kgs nuts in 2 days. After 5 days, Hari left the work. Ram took 8 more days to cut the rest of the nuts. If total of 58 kgs of nuts were cut, the time taken by Hari to cut 10 kg of nuts is

A) 1 day B) 2 days
C) 3 days D) 4 days
 
Answer & Explanation Answer: D) 4 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

1 2350
Q:

A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?

A) 12.5 days B) 100 days
C) 22.5 days D) 35 days
 
Answer & Explanation Answer: B) 100 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2350