Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Mahanath works 2 times as fast as Sahay. If Sahay can complete a job alone in 21 days, then in how many days can they together finish the job?

A) 7 days B) 6 days
C) 5 days D) 2 days
 
Answer & Explanation Answer: A) 7 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2219
Q:

A can paint a house in 45 days and B can do it in 15 days. Along with C, they did the job in 5 days only. Then, C alone can do the job in how many days?

A) 12 B) 9
C) 15 D) 8
 
Answer & Explanation Answer: B) 9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2218
Q:

P can make a table in 16 days while Q can make it in 20 days. Q started the work and did that work for 5 days. In how many days P can complete the remaining work?

 

A)  10 B)  12
C)  15 D) 18
 
Answer & Explanation Answer: B)  12

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 2213
Q:

Ehsaan is twice as good a worker as Kamal and together they finish a piece of work in 29 days. In how many days will Kamal, working alone, finish the work?

A) 58 B) 70
C) 87 D) 116
 
Answer & Explanation Answer: C) 87

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2209
Q:

A and B can do a piece of work in 24 and 30 daysrespectively. Both started the work and worked for 6 days.Then B leaves the work and C joins and the remaining workis completed by A and C together in 11 days. Find the days in which C alone can do the work

A) 80 B) 100
C) 120 D) 130
 
Answer & Explanation Answer: C) 120

Explanation:

(1/24 + 1/30) x 6 + (1/24 + 1/C) x 11 = 1

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2208
Q:

Robin can do a work alone in 9 days. Amit can do the same work alone in 6 days. Both of them finish the work together and they get a total Rs 2500. What isthe share (in Rs) of Robin?

A) 1700 B) 1200
C) 1500 D) 1000
 
Answer & Explanation Answer: D) 1000

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

2 2207
Q:

A mason can build a wall in 70 hours. After 7 hours he takes a break. What fraction of the wall is yet to be built?

A) 0.9 B) 0.8
C) 0.5 D) 0.75
 
Answer & Explanation Answer: A) 0.9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 2197
Q:

Pradeep has done 1/4th of a job in 14 days, Saquib completes the rest of the job in 56 days. In how many days can they together complete the job?

A) 64 days B) 32 days
C) 16 days D) 8 days
 
Answer & Explanation Answer: B) 32 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 2196