PMP Certification Questions

Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Qualitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement 

  • Risk management plan

  • Risk register


II.  Tools and Techniques



  • Risk probability and impact assesment

  • Probability and impact matrix

  • Risk data quality assessment

  • Risk categorization 

  • Risk Urgency assessment


III. Outputs



  • Risk register (updates)

Report Error

View answer Workspace Report Error Discuss

0 1640
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope control ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project scope management plan

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Change control system

  • Variance analysis

  • Replanning

  • Configuration management system


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure(updates)

  • WBS dictionary (updates)

  • Scope baseline (updates)

  • Requested changes

  • Recommended  corrective action

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1637
Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Manage stakeholders?

Answer

I. Inputs



  • Communications management plan 

  • Organizational process assets


II. Tools and Techniques



  • Communications methods

  • Issue logs


III. Outputs



  • Resolved issues

  • Approved change requests

  • Approved corrective actions 

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1637
Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Information Distribution?

Answer

I. Inputs



  • Communications management plan


II. Tools and Techniques



  • Communications skills 

  • Information gathering and retrieval systems

  • Information distribution methods

  • Lessons learned process


III. Outputs



  • Organizational process assets (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 1632
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Quantitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Risk management plan

  • Risk register

  • Project management plan


                 - Project schedule management plan


                 - Project cost management plan


II. Tools and Techniques



  • Data gathering and representation techniques

  • Quantitative risk analysis and modeling techniques


III. Outputs



  • Risk register (updates)

Report Error

View answer Workspace Report Error Discuss

0 1629
Q:

Project Scope Management

What are the Project Management Processes included in the Project Scope Management?

Answer

Scope Planning - Creating a project scope management plan that documents how the project scope will be defined,verified, controlled, and how the work breakdown structure (WBS) will be created and defined.


Scope Definition - Developing a detailed project scope statement as the basis for future project decisions.


Create WBS - Subdividing the major project deliverables and project work into smaller, more manageable components


Scope Verification - Formalizing acceptance of the completed project deliverables.


Scope Control - Controlling changes to the project scope.

Report Error

View answer Workspace Report Error Discuss

0 1621
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Human Resource Planning?

Answer

I. Inputs



  • Enterprise Environmental factors

  • Organizational process assets

  • Project management plan


                  - Activity resource requirements


II. Tools and Techniques



  • Organization charts and position descriptions 

  • Networking

  • Organizational theory


III. Outputs



  • Roles and responsibilities

  • Project organization charts

  • Staffing management plan

Report Error

View answer Workspace Report Error Discuss

0 1620
Q:

Project Time Management

What are the Project Management Processes included in the Project Time Management?

Answer

Activity Definition - Identifying the Specific schedule activities that need to be performed to produce the various project deliverables.


Activity Sequencing - Identifying and documenting dependencies among schedule activities


Activity Resource Estimating - Estimating the type and quantities of resources required to perform each schedule activity


Activity Duration Estimating - Estimating the number of work periods that will be needed to complete individual schedule activities


Schedule Development - Analyzing activity sequences, durations, resource requirements, and schedule constraints to creae the project schedule.


Schedule Control - Controlling changes to the project schedule

Report Error

View answer Workspace Report Error Discuss

0 1618