PMP Certification Questions

Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Human Resource Planning?

Answer

I. Inputs



  • Enterprise Environmental factors

  • Organizational process assets

  • Project management plan


                  - Activity resource requirements


II. Tools and Techniques



  • Organization charts and position descriptions 

  • Networking

  • Organizational theory


III. Outputs



  • Roles and responsibilities

  • Project organization charts

  • Staffing management plan

Report Error

View answer Workspace Report Error Discuss

0 2221
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Control ?

Answer

I. Inputs



  • Schedule management plan

  • Schedule baseline

  • Performance reports

  • Approved change requests


II. Tools and Techniques



  • Progress reporting

  • Schedule change control system

  • Performance measurement

  • Project management software

  • Variance analysis

  • Schedule comparision bar charts


III. Outputs



  • Schedule model data (updates)

  • Schedule baseline (updates)

  • Performance measurements

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Activity list (updates)

  • Activity attributes (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2205
Q:

Project Human Resource Management

What are the Project Management Processes included in the Project Human Resource Management?

Answer

Human Resource Planning - Identifying and documenting Project roles, responsibilities, and reporting relationships, as well as creating the staffing management plan.


Acquire Project Team - Obtaining the human resources needed to complete the project


Develop Project Team - Improving the competencies and interaction of team members to enhance project performance.


Manage Project Team - Tracking team member performance, providing feedback, resolving issues, and coordinating changes to enhance project performance.

Report Error

View answer Workspace Report Error Discuss

0 2203
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope control ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project scope management plan

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Change control system

  • Variance analysis

  • Replanning

  • Configuration management system


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure(updates)

  • WBS dictionary (updates)

  • Scope baseline (updates)

  • Requested changes

  • Recommended  corrective action

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2201
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Qualitative Risk Analysis?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement 

  • Risk management plan

  • Risk register


II.  Tools and Techniques



  • Risk probability and impact assesment

  • Probability and impact matrix

  • Risk data quality assessment

  • Risk categorization 

  • Risk Urgency assessment


III. Outputs



  • Risk register (updates)

Report Error

View answer Workspace Report Error Discuss

0 2191
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Development?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Project schedule network diagrams

  • Activity resource requirements

  • Resource calendars

  • Activity duration estimates 

  • Project management plan


                - RisK register


II. Tools and Techniques



  • Schedule network analysis

  • Critical path method

  • Schedule compression

  • What-if scenario analysis

  • Resource leveling

  • Critical chain method

  • Project management software

  • Applying calendars

  • Adjusting leads and lags 

  • Schedule model


III. Outputs



  • Project schedule

  • Schedule model data

  • Schedule baseline

  • Resource requirements (updates)

  • Activity attributes (updates)

  • Project calendar (updates)

  • Requested changes

  • Project management plan (updates)


                 - Schedule management plan(updates)

Report Error

View answer Workspace Report Error Discuss

0 2188
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Perform Quality Assurance?

Answer

I. Inputs



  • Quality management plan

  • Quality metrics

  • Process improvement plan 

  • Work performance information 

  • Approved change requests

  • Quality control measurements 

  • Implemented change requests

  • Implemented corrective actions 

  • Implemented defect repair

  • Implemented preventive actions 


II. Tools and Techniques



  • Quality planning tools and techniques

  • Quality audits

  • Process analysis 

  • Quality control tools and techniques


III. Outputs



  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2185
Q:

Project Management Process Groups

What are the Project Management Process Groups?

Answer

This section identifies and describes the five Project Management Process Groups required for any project. These five process Groups have clear dependencies and are performed in the same sequence on each project.


The five Process Groups are :


Initiating  Process Group - Defines and authorizes the project or a project phase


Planning Process Group - Defines and refines objectives, and plans the course of action required to attain the objectives and scope that the project was undertaken to address.


Executing Process Group - Integrates people and other resources to carry out the project management plan for the project


Monitoring and Controlling process Group - Regularly measures and monitors progress to identify variances from the project management plan so that corrective action can be taken when necessary to meet project objectives.


Closing Process Group - Formalizes acceptance of the product, service or result and brings the project or a project phase to an orderly end.

Report Error