PMP Certification Questions

Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Risk Monitoring and Control?

Answer

I. Inputs



  • Risk management plan

  • Risk register

  • Approved change requests

  • work performance information

  • performance reports


II. Tools and Techniques



  • Risk reassessment

  • Risk audits

  • Variance and trend analysis

  • Technical performance measurement

  • Reserve analysis

  • Status meetings


III. Outputs



  • Risk register (updates)

  • Requested changes

  • Recommended corrective actions

  • Recommended preventive actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2081
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Risk Identification?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Risk management plan

  • Project management plan


II. Tools and Techniques



  • Documentation reviews

  • Information gathering techniques

  • Checklist analysis

  • Assumptions analysis

  • Diagramming techniques


III. Outputs



  • Risk register

Report Error

View answer Workspace Report Error Discuss

0 2080
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Sequencing ?

Answer

I.Inputs



  • Project scope statement

  • Activity list

  • Activity attributes

  • Milestone list

  • Approved change requests


II. Tools and Techniques



  • Precedence Diagramming Method (PDM)

  • Arrow Diagramming Method (ADM)

  • Schedule network templates 

  • Dependency determination

  • Applying leads and lags 


III. Outputs



  • Project schedule network diagrams

  • Activity list (updates)

  • Activity attributes (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2062