Exams


Q:

The length of the room is 5.5m and width is 3.75m. Find the cost of paving the floor by slabs at the rate of Rs.800 per sq meter

A) Rs.16500 B) Rs.15500
C) Rs.17500 D) Rs.18500
 
Answer & Explanation Answer: A) Rs.16500

Explanation:

l=5.5m w=3.75m
area of the floor = 5.5 x 3.75 = 20.625 sq m
cost of paving = 800 x 20.625 = Rs. 16500

Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams
Job Role: Bank PO

18 28292
Q:

A watch gains 5 seconds in 3 minutes and was set right at 8 AM. What time will it show at 10 PM on the same day ?

A) 10 : 27 : 41 AM B) 8 : 51 : 04 AM
C) 9 : 45 : 15 PM D) 10 : 23 : 20 PM
 
Answer & Explanation Answer: D) 10 : 23 : 20 PM

Explanation:

The watch gains 5 seconds in 3 minutes = 100 seconds in 1 hour.

From 8 AM to 10 PM on the same day, time passed is 14 hours.

In 14 hours, the watch would have gained 1400 seconds or 23 minutes 20 seconds.

So, when the correct time is 10 PM, the watch would show 10 : 23 : 20 PM

Report Error

View Answer Report Error Discuss

Filed Under: Clocks
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

46 28283
Q:

Find the total surface area (in cm2) of a hemisphere of diameter 21 cm.

 

A) 1039.5   B) 844.5  
C) 637   D) 472
 
Answer & Explanation Answer: A) 1039.5  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Volume and Surface Area
Exam Prep: Bank Exams

2 28239
Q:

Arrange the given words in the sequence in which they occur in the dictionary.

 

1. Exception

2. Exceptional

3. Exchanging

4. Exchanged

5. Excess

 

A) 12543   B) 21453  
C) 42531   D) 32154
 
Answer & Explanation Answer: A) 12543  

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Logical Sequence of Words
Exam Prep: Bank Exams

1 28237
Q:

Which number will complete the series?

63, 72, 81, 90, ____, 108

A) 80 B) 99
C) 100 D) 117
 
Answer & Explanation Answer: B) 99

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Number Series
Exam Prep: Bank Exams

2 28237
Q:

The area of an equilateral triangle is 49√3 cm2. Find its side (in cm).

 

A) 7 B) 14
C) 28 D) 42
 
Answer & Explanation Answer: B) 14

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: Bank Exams

0 28188
Q:

A man traveled from the village to the post-office at the rate of 25 kmph and walked back at the rate of 4 kmph. If the whole journey took 5 hours 48 minutes, find the distance of the post-office from the village ?

A) 40 km B) 30 km
C) 20 km D) 10 km
 
Answer & Explanation Answer: C) 20 km

Explanation:

Average speed = 2aba+b, here a=25 b=4
= 2 x 25 x 4/(25+4) = 200/29 km/hr.

Distance covered in 5 hours 48 minutes
= Speed x time = (200/29)x (29/5) Distance covered in 5 hours 48 minutes = 40kms.

Distance of the post office from the village = (40/2) = 20 km.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

32 28187
Q:

A watch which gains 5 seconds in 3 minutes was set right at 7 a.m. In the afternoon of the same day, when the watch indicated quarter past 4 o'clock, the true time is:

A) 4pm B) 5pm
C) 6pm D) 7pm
 
Answer & Explanation Answer: A) 4pm

Explanation:

Time from 7 am to 4.15 pm  = 9 hrs 15 min = 374 hrs 

 

3 min. 5 sec. of this clock = 3 min. of the correct clock. 

 

Now 3min.5sec. is37720 hrs of this clock = 3 min.is120 hrs of the correct clock 

 

374 hrs of clock = 120×72037×374 hrs of the correct clock. 

 

  = 9 hrs of the correct clock. 

 

 The correct time is 9 hrs after 7 am. i.e., 4 pm.

Report Error

View Answer Report Error Discuss

Filed Under: Clocks
Exam Prep: Bank Exams
Job Role: Bank PO

89 28164