               Project Time Management - Processes
            
                           
                  
Describe the Inputs, Tools and Techniques, Outputs of Activity Duration Estimating ?
               
                      
         
             Answer
                        I. Inputs
- Enterprise environmental factors
- Organizational process assets
- Project scope statement
- Activity list
- Activity attributes
- Activity resource requirements
- Resource calendars
- Project management plan
               - Risk register
               - Activity cost estimates
II. Tools and Techniques
- Expert judgment
- Analogous  estimating
- Parametric estimating
- Three-point estimates 
- Reserve analysis
III. Outputs
- Activity duration estimates
- Activity attributes (updates)
 
         
         
         