Searching for "at"

Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Resource Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Activity list

  • Activity attributes

  • Resource availability

  • Project management plan


II. Tools and Techniques



  • Expert Judgment

  • Alternatives analysis

  • Published estimating data

  • Project management software

  • Bottom-up estimating


III. Outputs



  • Activity resource requirements

  • Activity atributes (updates)

  • Resource breakdown structure

  • Resource calendars (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

Q:

Project Time Management

What are the Project Management Processes included in the Project Time Management?

Answer

Activity Definition - Identifying the Specific schedule activities that need to be performed to produce the various project deliverables.


Activity Sequencing - Identifying and documenting dependencies among schedule activities


Activity Resource Estimating - Estimating the type and quantities of resources required to perform each schedule activity


Activity Duration Estimating - Estimating the number of work periods that will be needed to complete individual schedule activities


Schedule Development - Analyzing activity sequences, durations, resource requirements, and schedule constraints to creae the project schedule.


Schedule Control - Controlling changes to the project schedule

Report Error

View answer Workspace Report Error Discuss

Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope Verification ?

Answer

I. Inputs



  • Project scope statement

  • WBS dictionary

  • Project scope management plan

  • Deliverables


II. Tools and Techniques



  • Inspection


III. Outputs



  • Accepted  deliverables

  • Requested changes

  • Recommended corrective actions

Report Error

View answer Workspace Report Error Discuss

Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Create WBS ?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Project scope management  plan

  • Approved Change requests


II. Tools and Techniques



  • Work breakdown structure templates

  • Decomposition


III. Outputs



  • Project scope statement(updates)

  • Work breakdown structure

  • WBS dictionary

  • Scope baseline

  • Project scope management plan(updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

Q:

Project Scope Management

What are the Project Management Processes included in the Project Scope Management?

Answer

Scope Planning - Creating a project scope management plan that documents how the project scope will be defined,verified, controlled, and how the work breakdown structure (WBS) will be created and defined.


Scope Definition - Developing a detailed project scope statement as the basis for future project decisions.


Create WBS - Subdividing the major project deliverables and project work into smaller, more manageable components


Scope Verification - Formalizing acceptance of the completed project deliverables.


Scope Control - Controlling changes to the project scope.

Report Error

View answer Workspace Report Error Discuss

Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Close project Phase?

Answer

I. Inputs



  • Project management plan

  • Contract documentation

  • Enterprise environmental factors

  • Organizational process assets

  • Work performance information

  • Deliverables


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Administrative closure procedure

  • Contract closure procedure

  • Final product, service, or result

  • Organisational process assets (updates)

Report Error

View answer Workspace Report Error Discuss

Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Integrated Change Control Phase?

Answer

I. Inputs



  • Project management plan

  • Requested changes

  • Work performance information

  • Recommended preventive actions

  • Recommended corrective actions

  • Recommended defect repair

  • Deliverables


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Approved change requests

  • Rejected change requests

  • Project management plan(updates)

  • Project scope statement (updates)

  • Approved corrective actions

  • Approved preventive actions

  • Approved defect repair

  • Validated defect repair

  • Deliverables 

Report Error

View answer Workspace Report Error Discuss

Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Monitor and Control Project Work phase?

Answer

I. Inputs



  • Project management plan

  • Work performance information

  • Rejected Change requests


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Earned value technique

  • Expert Judgment


III. Outputs



  • Recommended corrective actions

  • Recommended preventive actions

  • Forecasts

  • Recommended defect repair

  • Requested changes 

Report Error