Searching for "he"

Q:

When data is encapsulated , which is the correct order?

A) Data, frame, packet, segment, bit B) Segment, data, packet, frame, bit
C) Data, segment, packet, frame, bit D) Data, segment, frame, packet, bit
 
Answer & Explanation Answer: C) Data, segment, packet, frame, bit

Explanation:

The encapsulation method is data, segment, packet, frame, bit.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

Q:

Which of the following devices do not operate at all levels of the OSI model?

A) Network management stations (NMSs) B) Routers
C) Web and application servers D) Network hosts
 
Answer & Explanation Answer: B) Routers

Explanation:

Routersoperate no higher than layer 3 of the OSI model.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

Q:

Which layer of the OSI model offers three different modes of communication : Simplex, half duplex, and full duplex?

A) Presentation B) Transport
C) Application D) Session
 
Answer & Explanation Answer: D) Session

Explanation:

The Session layer of the OSI model offers three different modes of communication : Simplex, half duplex, and full duplex.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

Q:

Routers operate at layer _____. LAN switches operate at layer ______. Ethernet hubs operate at layer _____. Word processing operates at layer _______.

A) 3, 3, 1, 7 B) 3, 2, 1, none
C) 3, 2, 1, 7 D) 3, 3, 2, none
 
Answer & Explanation Answer: B) 3, 2, 1, none

Explanation:

Routers operate at layer 3. LAN switches operate at layer 2. Ethernet hubs operate at layer 1. Word processing applications communicate to the Application layer interface, but do not operate at layer 7, so the answer would be none.

Report Error

View Answer Report Error Discuss

Filed Under: CCNA

Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Contract Closure?

Answer

I. Inputs



  • Procurement management plan

  • Contract management plan

  • Contract documentation

  • Contract closure procedure


II. Tools and Techniques



  • Procurement audits

  • Records management system


III. Outputs



  • Closed contracts

  • Organizational process assets (updates)

Report Error

View answer Workspace Report Error Discuss

Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Contract Administration?

Answer

I. Inputs



  • Contract

  • Contract management plan

  • Selected sellers

  • Performance reports

  • Approved change requests

  • Work performance information


II. Tools and Techniques



  • Contract change control system

  • Buyer-conducted performance review

  • Inspections and audits

  • Performance reporting

  • Payment system

  • Claims administration

  • Records management system

  • Information technology


III. Outputs



  • Contract documentation 

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)


                 - Procurement management plan


                 - Contract management plan

Report Error

View answer Workspace Report Error Discuss

Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Select Sellers?

Answer

I. Inputs



  • Organizational process assets

  • Procurement management plan

  • Evaluation criteria

  • Procurement document package

  • Proposals

  • Qualified sellers list

  • Project management plan


                 - Risk register


                 - Risk related contractual agreements


II. Tools and Techniques



  • Weighting system

  • Independent estimates

  • Screening system

  • Contract negotiation

  • Seller rating systems

  • Expert judgment

  • Proposal evaluation techniques


III. Outputs



  • Selected sellers

  • Contract

  • Contract management plan

  • Resource availability

  • Procurement management plan (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Request Seller Responses?

Answer

I. Inputs



  • Organizational process assets

  • Procurement management plan

  • Procurement documents


II. Tools and Techniques



  • Bidder conferences

  • Advertising

  • Develop qualified sellers list


III. Outputs



  • Qualified sellers list

  • Procurement document package

  • Proposals

Report Error

View answer Workspace Report Error Discuss