0
Q:
| A) 9.6 days | B) 10.5 days |
| C) 11.2 days | D) 16 days |
Answer: A) 9.6 days
Explanation:
Explanation:
A completed their work in 8 X 2 = 16 days
B completed their work in 8 X 3 = 24 days
A and B one day work1/16 + 1/245/48
A and B completed their work in 48/5 days = 9.6 days
Aptitude and Reasoning
General Knowledge
Puzzles
Interviews
Technical
Certifications
Exams
Job
Roles
True or False
Exams