15
Q:
| A) 1 day | B) 2 days |
| C) 5 days | D) None of these |
Answer: B) 2 days
Explanation:
Explanation:
Total work = 100+50 = 150man-days
In 8 days 100 man-days work has been completed. Now on 9th and 10th day there will be 25 workers. So in 2 days they wll complete additional 50 man- days work. Thus the work requires 2 more days.
Aptitude and Reasoning
General Knowledge
Puzzles
Interviews
Technical
Certifications
Exams
Job
Roles
True or False
Exams