Q:

P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together,working 8 hours a day,in how many days can they complete the work?

A) 60/11 B) 61/11
C) 71/11 D) 72/11

Answer:   A) 60/11



Explanation:

P can complete the work in (12 x 8) hrs = 96 hrs 

Q can complete the work in (8 x 10) hrs=80 hrs 

Therefore, P's 1 hour work=1/96   and Q's 1 hour work= 1/80

(P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs  

Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11

Q:

S, T and U together can complete a work in 30 days. If the ratio of efficiency of S, T and U is 20 : 15 : 12 respectively, then in how many days U alone can complete the same work?

A) 195/2 B) 235/2
C) 225/2 D) 215/2
 
Answer & Explanation Answer: B) 235/2

Explanation:
Report Error

View Answer Report Error Discuss

2 11
Q:

A and B together do a job in 6.75 days and A could do the job in 9 days if he worked alone. How many days would B take to do the job if he worked alone?

A) 27 B) 18
C) 24 D) 21
 
Answer & Explanation Answer: A) 27

Explanation:
Report Error

View Answer Report Error Discuss

0 18
Q:

A can paint a house in 42 days and B can do it in 21 days. Along with C, they can finish the job in 7 days only.C alone can do the painting job in how many days, ?

A) 9 B) 12
C) 14 D) 15
 
Answer & Explanation Answer: C) 14

Explanation:
Report Error

View Answer Report Error Discuss

0 7
Q:

A can do a work in 20 days and B in 10 days. If they work on it together for 5 days, then what fraction of work is left.

A) 4/9 B) 1/4
C) 1/5 D) 2/9
 
Answer & Explanation Answer: B) 1/4

Explanation:
Report Error

View Answer Report Error Discuss

0 56
Q:

A mason can build a wall in 70 hours. After 7 hours he takes a break. What fraction of the wall is yet to be built?

A) 0.9 B) 0.8
C) 0.5 D) 0.75
 
Answer & Explanation Answer: A) 0.9

Explanation:
Report Error

View Answer Report Error Discuss

1 50
Q:

A does 75% of a work in 25 days. He then calls in B and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?

A) 50 days B) 80 days
C) 24 days D) 37.5 days
 
Answer & Explanation Answer: A) 50 days

Explanation:
Report Error

View Answer Report Error Discuss

1 55
Q:

A does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 4 days. How long B alone would take to do the whole work?

A) 12.5 days B) 100 days
C) 22.5 days D) 35 days
 
Answer & Explanation Answer: B) 100 days

Explanation:
Report Error

View Answer Report Error Discuss

0 51
Q:

A does 60% of a work in 15 days. He then calls B, and they together finish the remaining work in 5 days. How long B alone would take to do the whole work?

A) 25 days B) 20 days
C) 80 days D) 24 days
 
Answer & Explanation Answer: A) 25 days

Explanation:
Report Error

View Answer Report Error Discuss

0 51