35
Q:

There are three boats B1, B2 and B3 working together they carry 60 people in each trip. One day an early morning B1 carried 50 people in few trips alone. When it stopped carrying the passengers B2 and B3 started carrying the people together. It took a total of 10 trips to carry 300 people by B1, B2 and B3. It is known that each day on an average 300 people cross the river using only one of the 3 boats B1, B2 and B3. How many trips it would take to B1, to carry 150 passengers alone?

A) 15 B) 30
C) 25 D) 10

Answer:   A) 15



Explanation:

Combined efficiency of all the three boats = 60 passenger/trip 

 

Now, consider option(a)

 

15 trips and 150 passengers means efficiency  of B1 =  10 passenger/trip 

 

which means in carrying 50 passengers B1 must has taken 5 trips. So the rest trips equal to 5 (10-5 = 5) in which B2 and B3 together carried remaining 250 (300 - 50 = 250) Passengers.

 

Therefore the efficiency of B2 and B3 = 250/5 = 50 passenger/trip  

 

Since, the combined efficiency of B1, B2 and B3 is 60. Which is same as given in the first statement hence option(a) is correct.

Q:

A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for ₹35000. The share of A (in ₹) in the contracted money will be:

 

A) 7000 B) 21000
C) 14000 D) 15000
 
Answer & Explanation Answer: C) 14000

Explanation:
Report Error

View Answer Report Error Discuss

4 378
Q:

A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for ₹35000. The share of B (in ₹) in the contracted money will be:

 

A) ₹15000 B) ₹14000
C) ₹21000 D) ₹7000
 
Answer & Explanation Answer: C) ₹21000

Explanation:
Report Error

View Answer Report Error Discuss

0 323
Q:

A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for ₹75000. The share of B (in ₹) in the contracted money will be:

 

A) 45,000 B) 30,000
C) 35,000 D) 40,000
 
Answer & Explanation Answer: A) 45,000

Explanation:
Report Error

View Answer Report Error Discuss

1 416
Q:

If 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?

 

A) 9 B) 18
C) 16 D) 12
 
Answer & Explanation Answer: D) 12

Explanation:
Report Error

View Answer Report Error Discuss

1 945
Q:

If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days?

 

A) 50 B) 60
C) 54 D) 45
 
Answer & Explanation Answer: B) 60

Explanation:
Report Error

View Answer Report Error Discuss

2 455
Q:

A can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many dayscan they finish 50% of the work, if they work together

 

A) 12 B) 6
C) 8 D) 9
 
Answer & Explanation Answer: B) 6

Explanation:
Report Error

View Answer Report Error Discuss

3 684
Q:

Shyam can complete a task in 12 days by working 10 hours a day. How many hours a day should he work to complete the task in 8 days?

 

A) 12 B) 15
C) 16 D) 14
 
Answer & Explanation Answer: B) 15

Explanation:
Report Error

View Answer Report Error Discuss

1 808
Q:

5 men and 8 women can complete a task in 34 days, whereas 4 men and 18 women can complete the same task in 28 days. In how many days can the same task be completed by 3 men and 5 women?

 

A) 56 B) 72
C) 64 D) 36
 
Answer & Explanation Answer: A) 56

Explanation:
Report Error

View Answer Report Error Discuss

6 982