Q:

If 7 spiders make 7 webs in 7 days, then 1 spider will make 1 web in how many days?

A) 1 B) 3
C) 7 D) 14
 
Answer & Explanation Answer: C) 7

Explanation:

Let the required number days be x.

Less spiders, More days (Indirect Proportion)

Less webs, Less days (Direct Proportion)

\inline {\color{Blue} \left.\begin{matrix} spiders &1:7 \\ webs & 7:1 \end{matrix}\right\}::7:x}

\inline {\color{Blue} \therefore } 1 x 7 x x = 7 x 1 x 7

=> x= 7

Report Error

View Answer Workspace Report Error Discuss

15 5433
Q:

2 men and 7 boys can do a piece of work in 14 days; 3 men and 8 boys can do the same in 11 days. Then, 8 men and 6 boys can do three times the amount of this work in 

A) 18 days B) 21 days
C) 24 days D) 30 days
 
Answer & Explanation Answer: B) 21 days

Explanation:

\inline \fn_jvn (2\times 14) men +(7\times 14)boys=(3\times 11)men+(8\times 11)boys

\inline \fn_jvn \Leftrightarrow  5 men= 10 boys  \inline \fn_jvn \Leftrightarrow  1man= 2 boys

\inline \fn_jvn \therefore  (2 men+ 7 boys) = (2 x 2 +7) boys = 11 boys

     ( 8 men + 6 boys) = (8 x 2 +6) boys = 22 boys.

Let the required  number of days be x.

More boys , Less days     (Indirect proportion)

More work , More days    (Direct proportion)

\inline \fn_jvn \left.\begin{matrix} Boys\: 22:11\\ Work\: 1:3 \end{matrix}\right\}::14:x  

\inline \fn_jvn \therefore \: \: (22\times 1\times x)=(11\times 3\times 14)   \inline \fn_jvn \Leftrightarrow  \inline \fn_jvn x= \frac{462}{22}=21

Hence, the required number of days = 21

Report Error

View Answer Workspace Report Error Discuss

9 5039
Q:

3 pumps working 8 hours a day, can empty a tank in 2 days. How many hours a day must 4 pumps work to empty the tank in 1 day?

A) 9 B) 10
C) 11 D) 12
 
Answer & Explanation Answer: D) 12

Explanation:

Let the required no of working hours per day be x.

More pumps , Less working hours per day  (Indirect Proportion)

Less days, More working hours per day      (Indirect Proportion)

\inline \fn_jvn \left.\begin{matrix} pumps\: 4:3\\ Days\; \; \; \; 1:2 \end{matrix}\right\}::8:x

\inline \fn_jvn \therefore  \inline \fn_jvn 4\times 1\times x= 3\times 2\times 8   \inline \fn_jvn \Leftrightarrow  X= \inline \fn_jvn \frac{3\times 2\times 8}{4}   \inline \fn_jvn \Leftrightarrow  x=12

Report Error

View Answer Workspace Report Error Discuss

6 5003
Q:

A certain number of men can finish a piece of work in 100 days. If there were 10 men less, it would take 10 days more for the work to be finished. How many men were there originally?

A) 75 B) 82
C) 100 D) 110
 
Answer & Explanation Answer: D) 110

Explanation:

Originally let there be x men.

Less men, More days     (Indirect Proportion)

\inline \fn_jvn \therefore  (x-10) : x  :: 100 :110   \inline \fn_jvn \Leftrightarrow  \inline \fn_jvn (x-10)\times 110=x\times 100  \inline \fn_jvn \Leftrightarrow  10x= 1100    \inline \fn_jvn \Leftrightarrow  x= 110

Report Error

View Answer Workspace Report Error Discuss

11 4796
Q:

If 20 men can build a wall 56 meters long in 6 days , what length of  a similar wall can be  built by 35 men in 3 days?

A) 46 B) 47
C) 48 D) 49
 
Answer & Explanation Answer: D) 49

Explanation:

Let the required length be x meters

More men, More length built     (Direct proportion)

Less days, Less length built      (Direct Proportion)

\inline \fn_jvn \left.\begin{matrix} Men\: \: \: 20:35\\ Days\: 6:3 \end{matrix}\right\}::56:x

\inline \fn_jvn \therefore  (20 x 6 x X)=(35 x 3 x 56) \inline \fn_jvn \Leftrightarrow  \inline \fn_jvn x=\frac{35\times 3\times 56}{120} =49

Hence, the required length is 49 m.

Report Error

View Answer Workspace Report Error Discuss

24 4669