Q:
| A) 9 | B) 10 |
| C) 11 | D) 12 |
Answer: D) 12
Explanation:
Explanation:
Let the required no of working hours per day be x.
More pumps , Less working hours per day (Indirect Proportion)
Less days, More working hours per day (Indirect Proportion)
=> (4 * 1 * x) = (3 * 2 * 8)
=> x=12