6
Q:

Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ?

A) 3 days B) 2 days
C) 6 days D) 12 days

Answer:   C) 6 days



Explanation:

From the given data,

12 children 16 days work,
One child’s one day work = 1/192.


8 adults 12 days work,
One adult’s one day’s work = 1/96.


Work done in 3 days = ((1/96) x 16 x 3) = 1/2


Remaining work = 1 – 1/2 = 1/2


(6 adults+ 4 children)’s 1 day’s work = 6/96 + 4/192 = 1/12

1/12 work is done by them in 1 day.

1/2 work is done by them in 12 x (1/2) = 6 days.

Q:

70000 a year is how much an hour?

A) 80 B) 8
C) 0.8 D) 0.08
 
Answer & Explanation Answer: B) 8

Explanation:

Given for year = 70000

=> 365 days = 70000

=> 365 x 24 hours = 70000

=>   1 hour = ?

70000/365x24 = 7.990 = 8

Report Error

View Answer Workspace Report Error Discuss

0 111
Q:

A, B and C can do a piece of work in 72, 48 and 36 days respectively. For first p/2 days, A & B work together and for next ((p+6))/3days all three worked together. Remaining 125/3% of work is completed by D in 10 days. If C & D worked together for p day then, what portion of work will be remained?

A) 1/5 B) 1/6
C) 1/7 D) 1/8
 
Answer & Explanation Answer: B) 1/6

Explanation:

Total work is given by L.C.M of 72, 48, 36

Total work = 144 units

Efficieny of A = 144/72 = 2 units/day

Efficieny of B = 144/48 = 3 units/day

Efficieny of C = 144/36 = 4 units/day

 

According to the given data,

2 x p/2 + 3 x p/2 + 2 x (p+6)/3 + 3 x (p+6)/3 + 4 x (p+6)/3 = 144 x (100 - 125/3) x 1/100

3p + 4.5p + 2p + 3p + 4p = 84 x 3 - 54

p = 198/16.5

p = 12 days.

 

Now, efficency of D = (144 x 125/3 x 1/100)/10 = 6 unit/day

(C+D) in p days = (4 + 6) x 12 = 120 unit

Remained part of work = (144-120)/144 = 1/6.

Report Error

View Answer Workspace Report Error Discuss

4 565
Q:

10 men and 15 women together can complete a work in 6 days. It takes 100 days for one man alone to complete the same work. How many days will be required for one woman alone to complete the same work?

A) 215 days B) 225 days
C) 235 days D) 240 days
 
Answer & Explanation Answer: B) 225 days

Explanation:

Given that

(10M + 15W) x 6 days = 1M x 100 days

=> 60M + 90W = 100M

=> 40M = 90W

=> 4M = 9W.

From the given data,

1M can do the work in 100 days

=> 4M can do the same work in 100/4= 25 days.

=> 9W can do the same work in 25 days.

=> 1W can do the same work in 25 x 9 = 225 days.

 

Hence, 1 woman can do the same work in 225 days.

Report Error

View Answer Workspace Report Error Discuss

8 928
Q:

A,B,C can complete a work in 15,20 and 30 respectively.They all work together for two days then A leave the work,B and C work some days and B leaves 2 days before completion of that work.how many days required to complete the whole work?

Answer

Given A,B,C can complete a work in 15,20 and 30 respectively.


The total work is given by the LCM of 15, 20, 30 i.e, 60.


A's 1 day work = 60/15 = 4 units


B's 1 day work = 60/20 = 3 units


C's 1 day work = 60/30 = 2 units


(A + B + C) worked for 2 days = (4 + 3 + 2) 2 = 18 units


 Let B + C worked for x days = (3 + 2) x = 5x units


C worked for 2 days = 2 x 2 = 4 units


Then, 18 + 5x + 4 = 60


22 + 5x = 60


5x = 38


x = 7.6


 


Therefore, total number of days taken to complete the work = 2 + 7.6 + 2 = 11.6 = 11 3/5 days.

Report Error

View answer Workspace Report Error Discuss

6 534
Q:

M, N and O can complete the work in 18, 36 and 54 days respectively. M started the work and worked for 8 days, then N and O joined him and they all worked together for some days. M left the job one day before completion of work. For how many days they all worked together?

A) 4 B) 5
C) 3 D) 6
 
Answer & Explanation Answer: B) 5

Explanation:

Let M, N and O worked together for x days.

From the given data,
M alone worked for 8 days
M,N,O worked for x days
N, O worked for 1 day

But given that
M alone can complete the work in 18 days
N alone can complete the work in 36 days
O alone can complete the work in 54 days

The total work can be the LCM of 18, 6, 54 = 108 units

M's 1 day work = 108/18 = 6 units
N's 1 day work = 108/36 = 3 units
O's 1 day work = 108/54 = 2 units

Now, the equation is
8 x 6 + 11x + 5 x 1 = 108
48 + 11x + 5 = 108
11x = 103 - 48
11x = 55
x = 5 days.

Hence, all M,N and O together worked for 5 days.

Report Error

View Answer Workspace Report Error Discuss

2 516
Q:

P, Q, and R can do a job in 12 days together.  If their efficiency of working be in the ratio 3 : 8 : 5, Find in what time Q can complete the same work alone?

A) 36 days B) 30 days
C) 24 days D) 22 days
 
Answer & Explanation Answer: A) 36 days

Explanation:

Given the ratio of efficiencies of P, Q & R are 3 : 8 : 5

Let the efficiencies of P, Q & R be 3x, 8x and 5x respectively

They can do work for 12 days.

=> Total work = 12 x 16x = 192x

 

Now, the required time taken by Q to complete the job alone = 162x8x = 24 days.

Report Error

View Answer Workspace Report Error Discuss

5 655
Q:

5 men and 3 boys can together cultivate a 23 acre field in 4 days and 3 men and 2 boys together can cultivate a 7 acre field in 2 days. How many boys will be needed together with 7 men, if they cultivate 45 acre of field in 6 days.

A) 6 B) 4
C) 2 D) 3
 
Answer & Explanation Answer: C) 2

Explanation:

Let work done by 1 man in i day be m

and Let work done by 1 boy in 1 day be b

From the given data,

4(5m + 3b) = 23

20m + 12b = 23....(1)

2(3m + 2b) = 7

6m + 4b = 7 ....(2)

By solving (1) & (2), we get

m = 1, b = 1/4

Let the number of required boys = n

6(7 1 + n x 1/4) = 45

=> n = 2.

Report Error

View Answer Workspace Report Error Discuss

5 664
Q:

The ratio of efficiencies of P, Q and R is 2 : 3 : 4. While P and R work on alternate days and Q work for all days. Now the work completed in total 10 days and the total amount they get is Rs. 1200. Find the amount of each person(respectively).

A) 200, 600, 400 B) 400, 600, 200
C) 600, 200, 400 D) 400, 200, 600
 
Answer & Explanation Answer: A) 200, 600, 400

Explanation:

Ratio of efficiencies of P, Q and R = 2 : 3 : 4

From the given data,

Number of working days of P, Q, R = 5 : 10 : 5

Hence, ratio of amount of p, Q, R = 2x5 : 3x10 : 4x5 = 10 : 30 : 20

Amounts of P, Q, R = 200, 600 and 400.

Report Error

View Answer Workspace Report Error Discuss

4 595