Quantitative Aptitude - Arithmetic Ability Questions

Q:

Tea worth of Rs. 135/kg & Rs. 126/kg are mixed with a third variety in the ratio 1: 1 : 2. If the mixture is worth Rs. 153 per kg, the price of the third variety per kg will be____?

A) Rs. 169.50 B) Rs.1700
C) Rs. 175.50 D) Rs. 180
 
Answer & Explanation Answer: C) Rs. 175.50

Explanation:

Since first second varieties are mixed in equal proportions, so their average price = Rs.(126+135)/2= Rs.130.50

So, Now the mixture is formed by mixing two varieties, one at Rs. 130.50 per kg and the other at say Rs. 'x' per kg in the ratio 2 : 2, i.e., 1 : 1. We have to find 'x'.

 

Cost of 1 kg tea of 1st kind         Cost of 1 kg tea of 2nd kind 

 

 

  

x-153/22.50 = 1  => x - 153 = 22.50  => x=175.50.

 Hence, price of the third variety = Rs.175.50 per kg.

Report Error

View Answer Report Error Discuss

Filed Under: Alligation or Mixture
Exam Prep: CAT , Bank Exams , AIEEE

556 83683
Q:

A merchant has 1000 kg of sugar part of which he sells at 8% profit and the rest at 18% profit. He gains 14% on the whole. The Quantity sold at 18% profit is

A) 400 kg B) 560 kg
C) 600 kg D) 640 kg
 
Answer & Explanation Answer: C) 600 kg

Explanation:

By the rule of alligation:

 

Profit of first part                         Profit of second part

 

 

So, ratio of 1st and 2nd parts = 4 : 6 = 2 : 3. 

 

Therefore, Quantity of 2nd kind = (3/5 x 1000)kg = 600 kg.

Report Error

View Answer Report Error Discuss

Filed Under: Alligation or Mixture

333 83354
Q:

Select the odd letters from the given alternatives.

 

A) ZXV B) GDA
C) NKH D) URO
 
Answer & Explanation Answer: A) ZXV

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: Bank Exams

0 83287
Q:

P can complete a work in 12 days working 8 hours a day.Q can complete the same work in 8 days working 10 hours a day. If both p and Q work together,working 8 hours a day,in how many days can they complete the work?

A) 60/11 B) 61/11
C) 71/11 D) 72/11
 
Answer & Explanation Answer: A) 60/11

Explanation:

P can complete the work in (12 x 8) hrs = 96 hrs 

Q can complete the work in (8 x 10) hrs=80 hrs 

Therefore, P's 1 hour work=1/96   and Q's 1 hour work= 1/80

(P+Q)'s 1 hour's work =(1/96) + (1/80) = 11/480. So both P and Q will finish the work in 480/11 hrs  

Therefore, Number of days of 8 hours each = (480/11) x (1/8) = 60/11

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

239 83176
Q:

Fill in the blanks

sinA = _____ x cosA

 

A) sinA B) tanA
C) cotA D) cosA
 
Answer & Explanation Answer: B) tanA

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

1 83059
Q:

Solve the following :

38 - (60 ÷ 5 x 16 - 8 ÷ 2 ÷ 3) =?

 

A) 22 B) 29
C) 30 D) 37
 
Answer & Explanation Answer: A) 22

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

2 83020
Q:

Compute of 1848 / 231 - 10 = ?

 

A) 2 B) -2
C) 188/221 D) 1884/221
 
Answer & Explanation Answer: B) -2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

2 82658
Q:

Find the Missing number in the given number series?

5, 9, 15, 23, ?, 45

A) 33 B) 29
C) 31 D) 35
 
Answer & Explanation Answer: A) 33

Explanation:

The given series follows a pattern that,

+4, +6, +8, +10, +12...

5

5 + 4 = 9

9 + 6 = 15

15 + 8 = 23

23 + 10 = 33

33 + 12 = 45

 

Hence, the missing number in the series is 33.

Report Error

View Answer Report Error Discuss

Filed Under: Odd Man Out
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

3 82570