Q:

A quality audit is

A) a structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures. B) the process of regularly evaluating overall project performance to provide confidence that the project will satisfy relevant quality standards.
C) an approach where the team members meet regularly to improve the process of quality control on their project. D) the process of determining the appropriate actions to increase the effectiveness and efficiency of the project to provide added benefits to project stakeholders.
 
Answer & Explanation Answer: A) a structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.

Explanation:

“A quality audit is a structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.”

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 4805
Q:

Which council is made up of 5 permanent members?

A) Trusteeship Council B) Security Council
C) General Assembly D) Economic and Social Council
 
Answer & Explanation Answer: A) Trusteeship Council

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Organisations

9 4804
Q:

Compressions and Rarefactions are characteristic of

A) Longitudinal waves B) Transverse waves
C) Both A & B D) Neither of A & B
 
Answer & Explanation Answer: A) Longitudinal waves

Explanation:

Compressions and Rarefactions are characteristic of Longitudinal waves.

The direction of vibration of the particles is in the same plane as in which the wave is propagating. The particles vibrate back and forth, about their mean positions.

Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

2 4803
Q:

Solve this logical Math puzzle?

Solve_this_math_puzzles1542974183.jpg image

A) 1 B) 0
C) 10 D) 5
 
Answer & Explanation Answer: A) 1

Explanation:

From the given data,

11+ 11 = 4 => 1 + 1  +  1 + 1 = 4

12 + 12 = 6 => 1 + 2  + 1 + 2 = 6

13 + 1 3 = 8 => 1 + 3  + 1 + 3 = 8


Similarly,

14 + 14 = 10 => 1 + 4  +  1 + 4  = 5 + 5 = 10

Report Error

View Answer Report Error Discuss

Filed Under: Math Puzzles
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

15 4799
Q:

Which is the longest snake in the world?

A) Black Mamba B) Puff Adder
C) Reticulated Python D) Anaconda
 
Answer & Explanation Answer: C) Reticulated Python

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Animals and Birds

38 4798
Q:

Describe how to perform Risk Analysis during software testing.

Answer

While a test plan is being created, risks involved in testing the product are to be taken into consideration along with possibility of their occurrence and the damage they may cause along with solutions; if any. Detailed study of this is called as Risk Analysis.


Some of the risks could be:


New Hardware 


New Technology 


New Automation Tool 


Sequence of code delivery 


Availability of application test resources 


Identify and describe the risk magnitude indicators: High, Medium and Low


High magnitude means the effect of the risk would be very high and non-tolerable. Company may face severe loss and its reputation is at risk. Must be tested.


Medium: tolerable but not desirable. Company may suffer financially but there is limited liability or loss of reputation. Should be tested.


Low: tolerable. Little or no external exposure. Little or no financial loss. Company’s reputation unaffected. Might be tested.


Three perspectives of Risk Assessment: Effect, Cause and Likelihood.


To assess risk by Effect, identify a condition, event or action and try to determine its impact.


To asses risk by Cause is opposite of by Effect. Begin by stating an undesirable event or condition and identify the set of events that could have permitted the condition to exist.


To asses risk by Likelihood is to determine the probability that a requirement will not be satisfied.

Report Error

View answer Workspace Report Error Discuss

Subject: Software Testing

0 4798
Q:

Typewriter was invented by

A) Shockley B) Sholes
C) Howe D) None of these
 
Answer & Explanation Answer: B) Sholes

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Inventions

1 4797
Q:

Which of the following group of elements are diamagnetic ?

A) Argon, copper, silver B) Hydrogen, argon, copper
C) Oxygen, copper, silver D) Hydrogen, oxygen, Argon
 
Answer & Explanation Answer: A) Argon, copper, silver

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: AIEEE

10 4797