Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Ram and Hari can cut 12 kgs nuts in 2 days. After 5 days, Hari left the work. Ram took 8 more days to cut the rest of the nuts. If total of 58 kgs of nuts were cut, the time taken by Hari to cut 10 kg of nuts is

A) 1 day B) 2 days
C) 3 days D) 4 days
 
Answer & Explanation Answer: D) 4 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work

1 2241
Q:

A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a day?

A) 59/11 B) 48/11
C) 70/11 D) 65/11
 
Answer & Explanation Answer: B) 48/11

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2230
Q:

A can finish a work in 7 days . B can finish the same work in 9 days . The days required to finish the work by both of them together.

A) 31/16 B) 47/16
C) 63/16 D) 79/16
 
Answer & Explanation Answer: C) 63/16

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2224
Q:

A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take to finish the rest of the job?

A) 20 B) 30
C) 18 D) 24
 
Answer & Explanation Answer: A) 20

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2217
Q:

Akash is 3 times as good a workman as Baldev and therefore is able to finish a job in 40 days less than Baldev. Working together, they can finish it in _____.

A) 15 days B) 60 days
C) 20 days D) 10 days
 
Answer & Explanation Answer: A) 15 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2202
Q:

30 women do half of the total work in 30 days. How many more women will be required to complete the remaining work in 10 days?

A) 45 B) 30
C) 60 D) 80
 
Answer & Explanation Answer: C) 60

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2202
Q:

A can do a work in 21 days and B in 42 days. If they work on it together for 7 days, then what fraction of work is left?

A) 1/3 B) 1/4
C) 2/3 D) 1/2
 
Answer & Explanation Answer: D) 1/2

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2193
Q:

Amit can complete a work in 25 days and Punit can complete the same work in 20 days. Punit alone worked at it for 10 days and then left the work. In how many days will Amit alone complete the remaining work?

A) 10.5 B) 11.5
C) 12.5 D) 13.5
 
Answer & Explanation Answer: C) 12.5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 2187