Quantitative Aptitude - Arithmetic Ability Questions

Q:

A can do a certain job in 12 days. B is 60% more efficient than A. Then B can do the same piece of work in

A) 8 days B) 7.5 days
C) 6.4 days D) 5.5 days
 
Answer & Explanation Answer: B) 7.5 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 2269
Q:

If the amount on a certain principal in 3 years at 12% rate of interest compounded annually is Rs 12,000, what will be the amount (in Rs) after the 4th year?

A) 14330 B) 15440
C) 13440 D) 14550
 
Answer & Explanation Answer: C) 13440

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Compound Interest
Exam Prep: Bank Exams

2 2269
Q:

If (x/y)a-4 = (y/x)2a-5, then what is the relation between x and y?

A) x > y B) Cannot be determined
C) x < y D) x = y
 
Answer & Explanation Answer: B) Cannot be determined

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

0 2269
Q:

The cost of leveling a triangular piece of land whose sides are 72 m. 30 m and 78 in respectively at the rate of 20 paisa per square metre is:

A) ₹ 220 B) ₹ 200
C) ₹ 216 D) ₹ 210
 
Answer & Explanation Answer: C) ₹ 216

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Area
Exam Prep: AIEEE , Bank Exams , CAT

2 2269
Q:

Marked price of an item is Rs 400. On purchase of 1 item discount is 6% and on purchase of 4 items discount is 24%. Rachita buys 5 items, what is the effective discount?

A) 34 percent B) 20.4 percent
C) 12.8 percent D) 23.25 percent
 
Answer & Explanation Answer: B) 20.4 percent

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: Bank Exams

2 2268
Q:

The standard deviation of the set {10, 11, 9, 11, 9} is

A) 1/√5 B) 2/√5
C) 3/√5 D) 0
 
Answer & Explanation Answer: B) 2/√5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Simplification
Exam Prep: Bank Exams

10 2267
Q:

8 men can complete a work in 16 days. 16 women can complete the same work in 24 days. In how many days can 4 men and 8 women complete the same work?

A) B)
C) D)
 
Answer & Explanation Answer:

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

10 2267
Q:

S, T and U can complete a work in 40, 48 and 60 days respectively. They received Rs 10800 to complete the work. They begin the work together but Tleft 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work alone. What is the share of S(in Rs) from total money?

A) 4320 B) 4500
C) 4860 D) 4960
 
Answer & Explanation Answer: C) 4860

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2267