Quantitative Aptitude - Arithmetic Ability Questions

Q:

If 4th december 1999 is Monday then what day is 3rd january 2000 ?

A) Sunday B) Monday
C) Tuesday D) Wednesday
 
Answer & Explanation Answer: D) Wednesday

Explanation:

Here from 4th December 1999 to 3rd January 2000,
there is a difference of 30 days.
Number of odd days = 30/7 = 2 odd days

Then no. of odd days = 2 => tuesday and wednesday(from monday).

Hence on 3rd january it is wednesday.

Report Error

View Answer Report Error Discuss

Filed Under: Calendar
Exam Prep: AIEEE , Bank Exams , CAT , GATE , GRE
Job Role: Bank Clerk , Bank PO

17 9689
Q:

Running 3/4th of his usual rate, a man is 15min late. Find his usual time in hours  ?

A) 2/3 hrs B) 3/4 hrs
C) 1/3 hrs D) 1/4 hrs
 
Answer & Explanation Answer: B) 3/4 hrs

Explanation:

Walking at 3/4th of usual rate implies that time taken would be 4/3th of the usual time. In other words, the time taken is 1/3rd more than his usual time

 

so 1/3rd of the usual time = 15min
or usual time = 3 x 15 = 45min = 45/60 hrs = 3/4 hrs.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Distance
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

5 9674
Q:

In a charity show tickets numbered consecutively from 101 through 350 are placed in a box. What is the probability that a ticket selected at random (blindly) will have a number with a hundredth digit of 2?

A) 0.25 B) 0.5
C) 0.75 D) 0.40
 
Answer & Explanation Answer: D) 0.40

Explanation:

250 numbers between 101 and 350 i.e. n(S)=250

n(E)=100th digits of 2 = 299−199 = 100

P(E)= n(E)/n(S) = 100/250 = 0.40

Report Error

View Answer Report Error Discuss

Filed Under: Probability

3 9662
Q:

X can complete the work in 10 days, Y can do the same in 15 days. If they are hired for 5 days to do the work together, what is the work that left unfinished?

A) 1/3 B) 2/3
C) 1/6 D) 5/6
 
Answer & Explanation Answer: C) 1/6

Explanation:

Given X can do in 10 days 

=> 1 day work of X = 1/10

 

Y can do in 15 days 

=> 1 day work of Y = 1/15

 

1day work of (X + Y) = 1/10 + 1/15 = 1/6

 

Given they are hired for 5 days

 => 5 days work of (X + Y) = 5 x 1/6 = 5/6

 Therefore, Unfinished work = 1 - 5/6 = 1/6 

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: GATE , CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

11 9661
Q:

If 35% of a number is 24 less than 50% of that number, then the number is ?

A) 80 B) 160
C) 100 D) 120
 
Answer & Explanation Answer: B) 160

Explanation:

Let the number be n. Then,

50% of n - 35% of n = 24

50/100 n - 35/100 n = 24

n = (24 x 100)/15 = 160.

Report Error

View Answer Report Error Discuss

Filed Under: Percentage
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Bank Clerk , Bank PO

8 9656
Q:

The probability of occurance of two two events A and B are 1/4 and 1/2 respectively. The probability of their simultaneous occurrance is 7/50. Find the probability that neither A nor B occurs.

A) 25/99 B) 39/100
C) 61/100 D) 17/100
 
Answer & Explanation Answer: B) 39/100

Explanation:

P ( neither A nor B) = PA and B  

 

=  PAB=  PAB1-PAB  

 

1-61100=39100

Report Error

View Answer Report Error Discuss

Filed Under: Probability

8 9633
Q:

A contractor undertook to complete a piece of work in 120 Days and employed 140 men upon it. At the end of 66 days only half of the work was done,so he put on 25 extra men. By how much time did he exceed the specific time ?

A) 2 days B) 3 days
C) 4 days D) 5 days
 
Answer & Explanation Answer: A) 2 days

Explanation:

work done=total number of person x number of days;
half of work done = 140 x 66;
For half of remaining work 25 extra men are added.
Therefore, total men for half work remaining = 140 + 25 = 165;
Let 2nd half work will be completed in K days;
140 x 66 = 165 x K
K = 122;
Hence, extra days => 122-120 = 2days.

Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: CAT , Bank Exams , AIEEE
Job Role: Bank PO , Bank Clerk

12 9630
Q:

The dates 3rd April, 2005; 6th August, 2010 and 5th December, 2013 when written in Date-Month-Year Form have a unique mathematical property. The Indian Independence Day of which year among the following has the same property?

A) 2017 B) 2016
C) 2018 D) 2015
 
Answer & Explanation Answer: A) 2017

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Calendar
Exam Prep: Bank Exams

51 9628