Time and Work Questions

FACTS  AND  FORMULAE  FOR  TIME  AND  WORK  QUESTIONS

 

 

1. If A can do a piece of work in n days, then A's 1 day's work =1n

2. If A’s 1 day's work =1n, then A can finish the work in n days.

 

3. A is thrice as good a workman as B, then:

Ratio of work done by A and B = 3 : 1.

Ratio of times taken by A and B to finish a work = 1 : 3.

 

NOTE : 

Efficiency1No of time units

 

 Efficiency × Time = Constant Work

 

Hence, Required time = WorkEfficiency

 

Whole work is always considered as 1, in terms of fraction and 100% , in terms of percentage.

In general, number of day's or hours = 100Efficiency

Q:

Mansukh can do a piece of work in 10 hours. If he is joined by Jayanti who is 50% more efficient, in what time will they together finish the work?

A) 2 hours B) 6 hours
C) 4 hours D) 3 hours
 
Answer & Explanation Answer: C) 4 hours

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

3 2404
Q:

A, B and C can together do a job in 9 days. C alone can do the job in 36 days. In how many days can A and B do 50% of the job working together?

A) 6 B) 12
C) 9 D) 15
 
Answer & Explanation Answer: A) 6

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2403
Q:

A can do a work in 36 days and B in 12 days. If they work on it together, then in how many days will they be able to do the work?

A) 8 B) 6
C) 10 D) 9
 
Answer & Explanation Answer: D) 9

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2400
Q:

P and Q can do a project in 150 and 100 days respectively. In how many days can they complete 60% of the project if they work together?

A) 12 days B) 72 days
C) 42 days D) 36 days
 
Answer & Explanation Answer: D) 36 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2395
Q:

A and B can complete a task in 1.5 days. However, A had to leave a few days before the task wascompleted and hence it took 2 days in all to complete the task. If A alone could complete the work in2.625 days, how many days before the work getting over did A leave?

A) 1.125 B) 0.625
C) 0.375 D) 0.875
 
Answer & Explanation Answer: D) 0.875

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

13 2389
Q:

Vijay can do a work in 8 hours. Vijay and Puneet together can do the same work in 6 hours. Puneet and Sachin together can do the same work in 4 hours. Sachin alone can complete the same work in how many hours?

A) 22/5 B) 28/5
C) 24/5 D) 26/5
 
Answer & Explanation Answer: C) 24/5

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

2 2386
Q:

A can do a piece of work in 10 days and B in 12 days. With help of C, they finish the work in 4 days. In how many days C alone can do the same work?

A) 12 B) 15
C) 18 D) 24
 
Answer & Explanation Answer: B) 15

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

1 2382
Q:

Madhur works 2 times faster than Sagar. If Sagar can complete a job alone in 18 days, then in how many days can they together finish the job?

A) 5 days B) 2 days
C) 6 days D) 4 days
 
Answer & Explanation Answer: C) 6 days

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Time and Work
Exam Prep: Bank Exams

0 2380