Why are CPM, GERT, and PERT not considered sufficient to create a project schedule?
         
       
      
      
      
          
      
      
          Answer & Explanation
         Answer: B) As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations         
         
Explanation: Answer A is tempting because it is true by definition, but Answer B is correct because it properly answers the question, in that these techniques do not take into account resource pool constraints. Answer C is incorrect because it provides possible early and late start and finish dates, but not the actual schedules. Answer D is incorrect because none of the the three are simulation techniques. 
       
      
      
      