Questions

Q:

The project life cycle can be broken into five phases that tend to overlap with each other frm one phase to another;however ,the control phase does not overlap with a specific phase. why?

A) Change control management is seperate from the other phases B) Change control management has a plan that can be usede throughout the initiation, planning, execution, and closeout of the project
C) Because the project sponsor is responsible for change control management , the project manager is not involved with that phase of the project D) Change control extends throughout the entire project from initiation to closeout
 
Answer & Explanation Answer: D) Change control extends throughout the entire project from initiation to closeout

Explanation:

Change control management is utilized from the begining to the end of the project in order to keep it focused with an emphasis on the time and budget. Answer A is incorrect because change control management is not seperate from the other phases. Answer B is incorrect because the control plan must be throughout the other phases of a project. Its usage is not optional, and consistent utilization is imperative to managing scope creep and other scope expansions. Answer C is incorrect because the project sponsors is generally not responsible for the change control documentation, although it should be involved in the buy-in and approval process.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

0 3591
Q:

Which day is celebrated as United nations Day every year

A) 7th April B) 24th October
C) 14th November D) 27th December
 
Answer & Explanation Answer: B) 24th October

Explanation:
Report Error

View Answer Report Error Discuss

4 3590
Q:

What will be output of following c code?

void main()
{
struct bitfield
{
unsigned a:5;
unsigned c:5;
unsigned b:6;

}bit;
char *p;
struct bitfield *ptr,bit1={1,3,3};
p=&bit1;
p++;
clrscr();
printf("%d",*p);
getch();
}

Answer

Output: 12

Explanation:
Binary value of a=1 is 00001 (in 5 bit)
Binary value of b=3 is 00011 (in 5 bit)
Binary value of c=3 is 000011 (in 6 bit)

In memory it is represented as:
Let address of bit1 is 500 which initialize to char pointer p. Since can is one byte data type so p++ will be 501. *p means content of memory location 501 which is (00001100) and its binary equivalent is 12. Hence output is 12.

Report Error

View answer Workspace Report Error Discuss

Subject: Programming

0 3588
Q:

At the center of the sun, fusion converts hydrogen into

A) Helium B) Plutonium
C) Water D) Carbon
 
Answer & Explanation Answer: A) Helium

Explanation:

At the center of the sun, nuclear fusion converts hydrogen into helium, energy, and neutrinos. Nuclear fusion is a reaction in which two or more atomic nuclei are combined to form one or more different atomic nuclei and subatomic particles (neutrons or protons).

At_the_center_of_the_sun,_fusion_converts_hydrogen_into1558676073.jpg image

Report Error

View Answer Report Error Discuss

Filed Under: Physics
Exam Prep: AIEEE , Bank Exams , CAT , GATE
Job Role: Analyst , Bank Clerk , Bank PO

1 3588
Q:

The gap between two communicating neurons is termed

A) Schwann cell B) Effector
C) Synaptic cleft D) Cell body
 
Answer & Explanation Answer: C) Synaptic cleft

Explanation:

A neuron or nerve cell is a cell that carries electrical impulses. Neurons are the basic units of the nervous system and its most important part is the brain. Every neuron is made of a cell body (also called a soma), dendrites and an axon. Dendrites and axons are nerve fibres.

 

The gap between two communicating neurons is termed Synaptic cleft.

Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank PO

4 3588
Q:

Amoeba belongs to the phylum

A) Protozoa B) Annelida
C) Porifera D) Platyhelminthes
 
Answer & Explanation Answer: A) Protozoa

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Biology

3 3587
Q:

Which day is observed as Rashtriya Ekta Diwas every year in India?

A) 31st July B) 31st March
C) 31st January D) 31st October
 
Answer & Explanation Answer: D) 31st October

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Important Days and Years
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Bank Clerk , Bank PO

8 3587
Q:

You are a project manager for the redevelopment of the Hoover Dam. Your team has been provided with the scope statement, but it lacks many description details. Your team is concerned because the project is in the initiation phase and it wants to postpone it until it has more information. As the project manager, you recommend that

A) The team should go forward, but be caution about the lack of details and the impact upon the timeline for the project B) The project should not go forward until the stakeholders agree about the scope and purpose of the project
C) The team should verify the scope and realize that more details will be available as more project characteristics are progressively elaborated. D) The team should review the project selection criteria for the Hoover Dam project
 
Answer & Explanation Answer: C) The team should verify the scope and realize that more details will be available as more project characteristics are progressively elaborated.

Explanation:

The project details and description will usually have less detail at the beginning of the project and will increase as the characteristics are progressively elaborated. Answer A is incorrect because the team should confirm that they understand the esence of the scope of the project, even if the details might be ambiguous at the beginning of the project. Answer B is incorrect because the project should go forward; however, the team should request further clarification of what the project scope entails. Answer D is incorrect because the project selection criteria should be established before the project begins.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification