PMP Certification Questions

Q:

Project Procurement Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Plan Purchase and Acquisitions?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Project management plan


                 - Risk register


                 - Risk - related contractual agreements


                 - Resource requirements


                 - Project schedule


                 - Activity cost estimates


                 - Cost baseline


II. Tools and Techniques



  • Make-or-buy analysis

  • Expert judgement

  • Contract types


III. Outputs



  • Procurement management plan

  • contract statement of work

  • make-or-buy decisions

  • Requested changes       

Report Error

View answer Workspace Report Error Discuss

0 2231
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Acquire Project Team?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Roles and responsibilities 

  • Project organization charts

  • Staffing management plan


II. Tools and Techniques



  • Pre-assignment

  • Negotiation

  • Acquisition

  • Virtual teams


III. Outputs



  • Project staff assignments

  • Resource availability

  • Staffing management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2226
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop Preliminary Project Scope Statement phase?

Answer

I. Inputs



  • Project Charter

  • Project Statement of work

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Preliminary project scope statement 

Report Error

View answer Workspace Report Error Discuss

0 2222
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Develop Project Team?

Answer

I. Inputs



  • Project staff assignments

  • Staffing management plan

  • Resource availability


II. Tools and Techniques



  • General management skills

  • Training

  • Team - building activities

  • Ground rules

  • Co-location

  • Recognition and rewards


III. outputs



  • Team performance assessment

Report Error

View answer Workspace Report Error Discuss

0 2209
Q:

Project Human Resource Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Manage Project Team?

Answer

I. Inputs



  • Organizational process assets

  • Project staff assignments

  • Roles and responsibilities

  • Project organization charts

  • Staffing management plan

  • Team performance assessment

  • Work performance information

  • Performance reports


II. Tools and Techniques



  • Observation and conversation

  • project performance appraisals

  • Conflict management

  • Issue log


III. Outputs



  • Requested changes

  • Recommended corrective actions

  • Recommended preventive actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2208
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Perform Quality Control?

Answer

I. Inputs



  • Quality management plan

  • Quality metrics 

  • Quality checklists

  • Organizational process assets

  • Work performance information

  • Approved change requests

  • Deliverables


II. Tools and Techniques



  • Cause and effect diagram

  • Control charts

  • Flow Charting

  • Histogram

  • Pareto chart

  • Run chart

  • Scatter diagram

  • Statistical sampling

  • Inspection

  • Defect repair review


III. Outputs



  • Quality control measurements

  • Validated defect repair

  • Quality baseline (updates)

  • Recommended corrective actions

  • Recommended preventive actions

  • Requested changes

  • Recommended defect repair

  • Organization process assets (updates)

  • Validated deliverables

  • Project management plan (updates)


 


 

Report Error

View answer Workspace Report Error Discuss

0 2196
Q:

Project Scope Management

What are the Project Management Processes included in the Project Scope Management?

Answer

Scope Planning - Creating a project scope management plan that documents how the project scope will be defined,verified, controlled, and how the work breakdown structure (WBS) will be created and defined.


Scope Definition - Developing a detailed project scope statement as the basis for future project decisions.


Create WBS - Subdividing the major project deliverables and project work into smaller, more manageable components


Scope Verification - Formalizing acceptance of the completed project deliverables.


Scope Control - Controlling changes to the project scope.

Report Error

View answer Workspace Report Error Discuss

0 2184
Q:

Project Life Cycle

What is the Project Life Cycle?

Answer

Project managers or the organization can divide projects into phases to provide better management control with appropriate links to the ongoing operations of the performing organization. Collectively, these phases are known as the project life cycle.