PMP Certification Questions

Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Performance Reporting?

Answer

I. Inputs



  • Work performance information

  • Performance measurements

  • Forecasted completion

  • Quality control measurements

  • Project management plan


                - Performance measurement baseline



  • Approved change requests

  • Deliverables


II. Tools and Techniques



  • Information presentation tools

  • Performance information gathering and compilation

  • Status review meetings

  • Time reporting systems

  • Cost reporting systems


III. Outputs



  • Performance reports

  • Forecasts

  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

Report Error

View answer Workspace Report Error Discuss

0 2110
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Perform Quality Assurance?

Answer

I. Inputs



  • Quality management plan

  • Quality metrics

  • Process improvement plan 

  • Work performance information 

  • Approved change requests

  • Quality control measurements 

  • Implemented change requests

  • Implemented corrective actions 

  • Implemented defect repair

  • Implemented preventive actions 


II. Tools and Techniques



  • Quality planning tools and techniques

  • Quality audits

  • Process analysis 

  • Quality control tools and techniques


III. Outputs



  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2108
Q:

Project Management Process Groups

What are the Project Management Process Groups?

Answer

This section identifies and describes the five Project Management Process Groups required for any project. These five process Groups have clear dependencies and are performed in the same sequence on each project.


The five Process Groups are :


Initiating  Process Group - Defines and authorizes the project or a project phase


Planning Process Group - Defines and refines objectives, and plans the course of action required to attain the objectives and scope that the project was undertaken to address.


Executing Process Group - Integrates people and other resources to carry out the project management plan for the project


Monitoring and Controlling process Group - Regularly measures and monitors progress to identify variances from the project management plan so that corrective action can be taken when necessary to meet project objectives.


Closing Process Group - Formalizes acceptance of the product, service or result and brings the project or a project phase to an orderly end.

Report Error

View answer Workspace Report Error Discuss

0 2106
Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Budgeting ?

Answer

I. Inputs



  • Project scope statement

  • Work breakdown structure

  • WBS dictionary

  • Activity cost estimates

  • Activity cost estimate supporting detail

  • Project schedule 

  • Resource calendars 

  • Contract

  • Cost management plan


II. Tools and Techniques



  • Cost aggregation

  • Reserve analysis

  • Parametric estimating 

  • Funding limit reconciliation


III. Outputs



  • Cost baseline 

  • Project funding requirements 

  • Cost management plan (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2099
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Resource Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Activity list

  • Activity attributes

  • Resource availability

  • Project management plan


II. Tools and Techniques



  • Expert Judgment

  • Alternatives analysis

  • Published estimating data

  • Project management software

  • Bottom-up estimating


III. Outputs



  • Activity resource requirements

  • Activity atributes (updates)

  • Resource breakdown structure

  • Resource calendars (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2094
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Develop project management plan phase?

Answer

I. Inputs



  • Preliminary project scope statement

  • Project management processes

  • Enterprise environmental factors

  • Organizational process assets


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Expert Judgment


III. Outputs



  • Project management plan

Report Error

View answer Workspace Report Error Discuss

0 2093
Q:

Project Human Resource Management

What are the Project Management Processes included in the Project Human Resource Management?

Answer

Human Resource Planning - Identifying and documenting Project roles, responsibilities, and reporting relationships, as well as creating the staffing management plan.


Acquire Project Team - Obtaining the human resources needed to complete the project


Develop Project Team - Improving the competencies and interaction of team members to enhance project performance.


Manage Project Team - Tracking team member performance, providing feedback, resolving issues, and coordinating changes to enhance project performance.

Report Error

View answer Workspace Report Error Discuss

0 2091
Q:

Project Cost Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Cost Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets 

  • Project scope statement

  • Work breakdown structure

  • WBS dictionary 

  • Project management plan


             - Schedule management plan


             - Staffing management plan


             - Risk register


II. Tools and Techniques



  • Analogous estimating

  • Determine resource cost rates

  • Bottom-up estimating

  • Parametric estimating

  • Project management software

  • Vendor bid analysis

  • Reserve analysis

  • Cost of quality


III. Outputs



  • Activity cost estimates 

  • Activity cost estimate supporting detail 

  • Requested changes

  • Cost management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2088