Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Sequencing ?

Answer

I.Inputs



  • Project scope statement

  • Activity list

  • Activity attributes

  • Milestone list

  • Approved change requests


II. Tools and Techniques



  • Precedence Diagramming Method (PDM)

  • Arrow Diagramming Method (ADM)

  • Schedule network templates 

  • Dependency determination

  • Applying leads and lags 


III. Outputs



  • Project schedule network diagrams

  • Activity list (updates)

  • Activity attributes (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss

0 2037
Q:

Project Integration Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Monitor and Control Project Work phase?

Answer

I. Inputs



  • Project management plan

  • Work performance information

  • Rejected Change requests


II. Tools and Techniques



  • Project management methodology

  • Project management information system

  • Earned value technique

  • Expert Judgment


III. Outputs



  • Recommended corrective actions

  • Recommended preventive actions

  • Forecasts

  • Recommended defect repair

  • Requested changes 

Report Error

View answer Workspace Report Error Discuss

1 2037
Q:

Executing Process Group

What are the Project Management Processes included in the Executing Process Group?

Answer


    • Direct and Manage Project Execution

    • Perform Quality Assurance

    • Acquire Project Team

    • Develop Project Team

    • Information Distribution

    • Request Seller Responses

    • Select Sellers


Report Error

View answer Workspace Report Error Discuss

0 2036