Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Duration Estimating ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Activity resource requirements

  • Resource calendars

  • Project management plan


               - Risk register


               - Activity cost estimates


II. Tools and Techniques



  • Expert judgment

  • Analogous  estimating

  • Parametric estimating

  • Three-point estimates 

  • Reserve analysis


III. Outputs



  • Activity duration estimates

  • Activity attributes (updates)

Report Error

View answer Workspace Report Error Discuss

0 1576
Q:

Project Risk Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Risk Identification?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Risk management plan

  • Project management plan


II. Tools and Techniques



  • Documentation reviews

  • Information gathering techniques

  • Checklist analysis

  • Assumptions analysis

  • Diagramming techniques


III. Outputs



  • Risk register

Report Error

View answer Workspace Report Error Discuss

0 1571
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope Planning ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project charter

  • Priliminary project scope statement


II. Tools and Techniques



  • Expert Judgment

  • Templates, forms, standards


III. Outputs



  • Project scope management plan

Report Error

View answer Workspace Report Error Discuss

0 1568