Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Manage stakeholders?

Answer

I. Inputs



  • Communications management plan 

  • Organizational process assets


II. Tools and Techniques



  • Communications methods

  • Issue logs


III. Outputs



  • Resolved issues

  • Approved change requests

  • Approved corrective actions 

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 1979
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope Planning ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project charter

  • Priliminary project scope statement


II. Tools and Techniques



  • Expert Judgment

  • Templates, forms, standards


III. Outputs



  • Project scope management plan

Report Error

View answer Workspace Report Error Discuss

0 1965
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Activity Sequencing ?

Answer

I.Inputs



  • Project scope statement

  • Activity list

  • Activity attributes

  • Milestone list

  • Approved change requests


II. Tools and Techniques



  • Precedence Diagramming Method (PDM)

  • Arrow Diagramming Method (ADM)

  • Schedule network templates 

  • Dependency determination

  • Applying leads and lags 


III. Outputs



  • Project schedule network diagrams

  • Activity list (updates)

  • Activity attributes (updates)

  • Requested changes

Report Error

View answer Workspace Report Error Discuss