PMP Certification Questions

Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope Verification ?

Answer

I. Inputs



  • Project scope statement

  • WBS dictionary

  • Project scope management plan

  • Deliverables


II. Tools and Techniques



  • Inspection


III. Outputs



  • Accepted  deliverables

  • Requested changes

  • Recommended corrective actions

Report Error

View answer Workspace Report Error Discuss

0 1747
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope Planning ?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project charter

  • Priliminary project scope statement


II. Tools and Techniques



  • Expert Judgment

  • Templates, forms, standards


III. Outputs



  • Project scope management plan

Report Error

View answer Workspace Report Error Discuss

0 1747
Q:

Project Communications Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Communications planning?

Answer

I. Inputs



  • Enterprise environmental factors

  • Organizational process assets

  • Project scope statement

  • Project management plan


                   - Constraints


                   - Assumptions


II. Tools and Techniques



  • Communications requirements analysis

  • Communications technology


III. Outputs



  • Communications management plan

Report Error

View answer Workspace Report Error Discuss

0 1745