Q:

Subject matters experts (SMEs) are resources that are imperative to the succes of a project. Many times, project managers are not experts in the areas they are managing and frequently must rely upon other's expertise. In which scope - management process are SMEs first used?

A) Scope planning B) Scope definition
C) Initiation D) Scope verification
 
Answer & Explanation Answer: C) Initiation

Explanation:

Initiation is the first step in the scope management process, and expert judgment is one of the techniques routinely utilized. Answers A, B, and D are incorrect because they would come after the initiation process.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

A project charter is one of the key deliverables to come from the initiation process. The project charter should by issued by 

A) one or more functional managers B) The head of the performing organization
C) A manager external to the project D) The CFO
 
Answer & Explanation Answer: C) A manager external to the project

Explanation:

The other answers could be accurate in specific situations, but their role alone does not meet the keyb criterion of being "external" to the project team. Answers A, B, and D are incorrect because these individuals are not external to the project.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Sometimes project managers forget all of the expenses that they can incur on a project, such as capital resources and assets. This can have an impact upon their budgets and the economic return on the project. A cost that has been incurred and cannot be reversed is known as a 

A) Fixed Cost B) Direct Cost
C) Variable Cost D) Sunk Cost
 
Answer & Explanation Answer: D) Sunk Cost

Explanation:

Answer D is correct because a sunk cost is a project expense that will eventualy need to be paid. Answer A is incorrect because a fixed cost remains constant, regardless of any change in a company's activity. Answer B is incorrect because direct cost can be directly linked to producing specific goods or services. Answer C is incorrect because a variable cost changes in proportion to a change in the company's activity or business.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

One of the goals of management by objectives (MBO) is to ensure that objectives of one level within an organization are supportive of and aligned with the objectives of another level of the organization. This methodology has been popular within some organizations as they define their culture. Which of the following is not true about MBO?

A) It has a top-down orientation B) Corrective actions are not part of the process
C) You need to establish clear and achievable objectives D) MBO is a natural fit for Project Management
 
Answer & Explanation Answer: B) Corrective actions are not part of the process

Explanation:

Corrective actions are part of the process after establishing objectives and checking on the objectives. The next step is to take corrective actions. Answers A, C, D are true statements and therfore are incorrect for this question.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

The software development life cycle begins with a proof of concept and progress into the build, test, and acceptance phases as the project develops. Some times, differences between stakeholders can develop into conflict, which impacts the customer. As a trained, professional project manager, how do you handle this situation and resolve the customer's concerns?

A) Let the customer vent and take notes B) Schedule a meeting
C) Develope a change request for the customer D) Resolve the matter in favour of the customer
 
Answer & Explanation Answer: D) Resolve the matter in favour of the customer

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

The project life cycle can be broken into five phases that tend to overlap with each other frm one phase to another;however ,the control phase does not overlap with a specific phase. why?

A) Change control management is seperate from the other phases B) Change control management has a plan that can be usede throughout the initiation, planning, execution, and closeout of the project
C) Because the project sponsor is responsible for change control management , the project manager is not involved with that phase of the project D) Change control extends throughout the entire project from initiation to closeout
 
Answer & Explanation Answer: D) Change control extends throughout the entire project from initiation to closeout

Explanation:

Change control management is utilized from the begining to the end of the project in order to keep it focused with an emphasis on the time and budget. Answer A is incorrect because change control management is not seperate from the other phases. Answer B is incorrect because the control plan must be throughout the other phases of a project. Its usage is not optional, and consistent utilization is imperative to managing scope creep and other scope expansions. Answer C is incorrect because the project sponsors is generally not responsible for the change control documentation, although it should be involved in the buy-in and approval process.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

Management by projects views aspects of ongoing operations as projects in order to apply Project Management techniques to them. This can be used to describe an oranizational approach to the management of ongoing operations. Why would a company want to utilize this methodology on nonprojects?

A) To keep project managers employed B) To provide better estimates about durations
C) To allow the utilization of PM tools, such as earned value, to calculate ROI D) To specify the different phases within the operations
 
Answer & Explanation Answer: C) To allow the utilization of PM tools, such as earned value, to calculate ROI

Explanation:

Answer A is incorrect because project managers are not effectively utilized if they are always scheduling and coordinating resources for daily operations. Answer B is incorrect because project managers are not the best resource for providing estimates on daily operations and time allocations;people doing the actual work are the best resources. Answer D is incorrect because you do not specify different phases of ongoing operations.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

You have recently been promoted to a project manager for a clinical testing facility. The team is developing a new product that will cut down on testing interval requirements for a new seizure management medication. After you become involved with the project, you decide to add more research reports, which the customer did not request. This is an example of 

A) Good customer service scope B) Scope creep
C) Due diligence D) Gold Plating
 
Answer & Explanation Answer: D) Gold Plating

Explanation:

Answer A is incorrect because you are providing a service that the customer did not request; therefore, it might not be important to her and unnecessary. Answer B is incorrect because scope creep is generally an expansion of the scope of the project at the customer's request and the customer did not request these reports. Answer C is incorrect because an additional report does not always mean increased diligence with a project.

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification