Q:
| A) To keep project managers employed | B) To provide better estimates about durations |
| C) To allow the utilization of PM tools, such as earned value, to calculate ROI | D) To specify the different phases within the operations |
Answer: C) To allow the utilization of PM tools, such as earned value, to calculate ROI
Explanation:
Explanation:
Answer A is incorrect because project managers are not effectively utilized if they are always scheduling and coordinating resources for daily operations. Answer B is incorrect because project managers are not the best resource for providing estimates on daily operations and time allocations;people doing the actual work are the best resources. Answer D is incorrect because you do not specify different phases of ongoing operations.