19
Q:
| A) Sponser | B) Stake holder |
| C) Customer | D) None |
Answer: D) None
Explanation:
Explanation:
The project initiator or sponsor should be at a level that is appropriate to funding the project. They will either create the project charter or delegate that duty to the project manager.
Projects are authorized by someone external to the project such as a sponsor, PMO or portfolio steering committee.