Assuming that the phases in a project are concept, development, implementation and termination, which phase typically has the highest degree of uncertainty?

A) Concept B) Development
C) Implementation D) Termination
 
Answer & Explanation Answer: A) Concept

Explanation:

The first phase in a project always has the greatest degree of uncertainty because at this point in time the product is the least well defined. PMBOK, See figure 2-2. [2.1.1]

Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

An accepted deadline for a project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize?

A) Additional resources using the contingency fund B) Escalation approval to use contingency funding
C) Team overtime to meet schedule D) Corrective action based on causes
 
Answer & Explanation Answer: D) Corrective action based on causes

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: PMP Certification

Q:

So if md5( ) generates the most secure hash, why would you ever use the less secure crc32( ) and sha1( )?

Answer Crypto usage in PHP is simple, but that doesn’t mean it’s free. First off, depending on the data that you’re encrypting, you might have reasons to store a 32-bit value in the database instead of the 160-bit value to save on space. Second, the more secure the crypto is, the longer is the computation time to deliver the hash value. A high volume site might be significantly slowed down, if frequent md5() generation is required.
Report Error

View answer Workspace Report Error Discuss

Subject: PHP