Q:
| A) Concept | B) Development |
| C) Implementation | D) Termination |
Answer: A) Concept
Explanation:
Explanation:
The first phase in a project always has the greatest degree of uncertainty because at this point in time the product is the least well defined. PMBOK, See figure 2-2. [2.1.1]