Q:

48 people could complete a task in 17 days. After 6 days, 4 of the workers left. How many days from then will it take to complete the task?

A) 12 B) 13
C) 15 D) 16

Answer:   A) 12



Explanation:

Given, 48 people can do a work in 17 days. So total work = 48 x 17 = 816
Work done by 48 people in 6 days = 288.

The remaining work = 816 - 288 = 528
After 6 days four workers left. So number of people working is 44
Total number of days required for 44 men to complete the remaining work = 528/44 = 12

Q:

Akash is 3 times as good a workman as Baldev and therefore is able to finish a job in 40 days less than Baldev. Working together, they can finish it in _____.

A) 15 days B) 60 days
C) 20 days D) 10 days
 
Answer & Explanation Answer: A) 15 days

Explanation:
Report Error

View Answer Report Error Discuss

0 1
Q:

A can do a work in 12 days and B in 24 days. If they work on it together for 4 days, then what fraction of work is left?

A) 1/3 B) 1/2
C) 1/4 D) 1/5
 
Answer & Explanation Answer: B) 1/2

Explanation:
Report Error

View Answer Report Error Discuss

0 23
Q:

P, Q and R together can make a table in 40 minutes. P and Q together can make it in 60 minutes. How much time (in minutes) will R alone take to make the table?

A) 100 B) 120
C) 90 D) 150
 
Answer & Explanation Answer: B) 120

Explanation:
Report Error

View Answer Report Error Discuss

0 22
Q:

A can do a work in 15 days and B in 9 days. If they work on it together for 5 days, then what fraction of work is left?

A) 1/6 B) 3/7
C) 1/3 D) 1/9
 
Answer & Explanation Answer: D) 1/9

Explanation:
Report Error

View Answer Report Error Discuss

0 53
Q:

X, Y and Z can do a piece of work in 30,40 and 50 days respectively. All three of them began the work together but Y left 4 days before completion of the work. In how many days was the work completed?

A) 660/47 B) 640/47
C) 680/47 D) 665/47
 
Answer & Explanation Answer: A) 660/47

Explanation:
Report Error

View Answer Report Error Discuss

1 38
Q:

A and B together do a job in 12 days and A could do the job in 20 days if he worked alone. How many days would B take to do the job if he worked alone?

A) 30 B) 25
C) 24 D) 15
 
Answer & Explanation Answer: A) 30

Explanation:
Report Error

View Answer Report Error Discuss

1 84
Q:

A, B and C can do a job working alone in 12, 16 and 24 days respectively. In how many days they can do the job if they worked together?

A) 16/3 B) 15/4
C) 17/3 D) 19/4
 
Answer & Explanation Answer: A) 16/3

Explanation:
Report Error

View Answer Report Error Discuss

0 73
Q:

A, B and C can do a job working alone in 12, 16 and 24 days respectively. In how many days they can do the job if they worked together?

A) 16/3 B) 15/4
C) 17/3 D) 19/4
 
Answer & Explanation Answer: A) 16/3