80
Q:

A,B,C together can do a piece of work in 10 days.All the three started workingat it together and after 4 days,A left.Then,B and C together completed the work in 10 more days.In how many days can complete a work alone ?

A) 25 B) 24
C) 23 D) 21

Answer:   A) 25



Explanation:

(A+B+C) do 1 work in 10 days.

So (A+B+C)'s 1 day work=1/10 and as they work together for 4 days so workdone by them in 4 days=4/10=2/5


Remaining work=1-2/5=3/5

 

(B+C) take 10 more days to complete 3/5 work. So( B+C)'s 1 day work=3/50


Now A'S 1 day work=(A+B+C)'s 1 day work - (B+C)'s 1 day work=1/10-3/50=1/25

A does 1/25 work in in 1 day

Therefore 1 work in 25 days.

Q:

X and Y together can do a piece of work in 30 days. Y and Z together can do the work in 20 days. X starts the work and works for 15 days then Y takes that work and works for 27 days. Finally Z finishes the remaining work in 9 days. In how many days Y alone can complete the entire work?

 

A) 60 B) 45
C) 50 D) 65
 
Answer & Explanation Answer: A) 60

Explanation:
Report Error

View Answer Report Error Discuss

0 87
Q:

Both X and Y together can complete a work in 12 days and Y alone can complete the same work in 30 days. In how many days will X alone complete the work?

 

A) 15 B) 20
C) 18 D) 16
 
Answer & Explanation Answer: B) 20

Explanation:
Report Error

View Answer Report Error Discuss

0 123
Q:

A, B and C together can complete a work in 25 days. If the ratio of efficiency of A, B and C is 15 : 10 : 6 respectively, then in how many days C alone can complete the same work?

A) 727/6 B) 725/6
C) 775/6 D) 745/6
 
Answer & Explanation Answer: C) 775/6

Explanation:
Report Error

View Answer Report Error Discuss

0 242
Q:

Manish is four times as efficient as Puneet. Manish takes 90 days less than Puneet to complete a book. If both of them work together, then in how many days the book will be completed?

A) 28 B) 25
C) 24 D) 30
 
Answer & Explanation Answer: C) 24

Explanation:
Report Error

View Answer Report Error Discuss

2 283
Q:

Manish can complete a work in 21 days and Karan can complete the same work in 28 days. If both together work for 7 days, then what fraction of total work is left?

 

A) 3/5 B) 2/3
C) 7/12 D) 5/12
 
Answer & Explanation Answer: D) 5/12

Explanation:
Report Error

View Answer Report Error Discuss

2 256
Q:

20 boys do one fourth of work in 25 days. How many more boys will be required to complete the remaining work in 50 days?

 

A) 8 B) 10
C) 15 D) 20
 
Answer & Explanation Answer: B) 10

Explanation:
Report Error

View Answer Report Error Discuss

1 189
Q:

Sumit is 28% less efficient than Amit. If Amit can make a wall in 54 days, then Sumit can complete the same work in how many days?

 

A) 75 B) 70
C) 72 D) 76
 
Answer & Explanation Answer: A) 75

Explanation:
Report Error

View Answer Report Error Discuss

1 312
Q:

Vijay can do a work in 8 hours. Vijay and Puneet together can do the same work in 6 hours. Puneet and Sachin together can do the same work in 4 hours. Sachin alone can complete the same work in how many hours?

A) 22/5 B) 28/5
C) 24/5 D) 26/5
 
Answer & Explanation Answer: C) 24/5

Explanation:
Report Error

View Answer Report Error Discuss

1 252