16
Q:

A can build a wall in 16 days while B can destroy it in 8 days. A worked for 5 days. Then B joined with A for the next 2 days. Find in how many days could A build the remaining wall ?

A) 12 days B) 14 days
C) 13 days D) 16 days

Answer:   C) 13 days



Explanation:

Now, Total work = LCM(16, 8) = 48

A's one day work = + 48/16 = + 3

B's one day work = - 48/8 = -6

Given A worked for 5 days to build the wall => 5 days work = 5 x 3 = + 15

2days B joined with A in working = 2(3 - 6) = - 6

Remaining Work of building wall = 48 - (15 - 6) = 39

Now this remaining work will be done by A in = 39/3 = 13 days.

Q:

Amit and Sunil together can complete a work in 9 days, Sunil and Dinesh together can complete the same work in 12 days, and Amit and Dinesh together can complete the same work in 18 days. In how many days will they complete the work if Amit, Sunil and Dinesh work together?

 

A) 12 days B) 8 days
C) 14 days D) 16 days
 
Answer & Explanation Answer: B) 8 days

Explanation:
Report Error

View Answer Report Error Discuss

1 172
Q:

X can complete a work in 27 days and Y can do the same work in half of the time taken by X. Working together what part of the same work can they complete in a day?

 

A) 1/9 B) 1/6
C) 1/12 D) 2/27
 
Answer & Explanation Answer: A) 1/9

Explanation:
Report Error

View Answer Report Error Discuss

2 73
Q:

A, B and C can individually complete a task in 20 days, 16 days and 30 days, respectively. If A and B started working on the task, and they worked for 4 days and left, then the number of days required by C to finish the remaining task is:

 

A) 16.5 days B) 13 days
C) 10 days D) 12.5 days
 
Answer & Explanation Answer: A) 16.5 days

Explanation:
Report Error

View Answer Report Error Discuss

4 111
Q:

A can do a piece of work in 6 days. B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work ?

 

A) 18 B) 8
C) 12 D) 16
 
Answer & Explanation Answer: A) 18

Explanation:
Report Error

View Answer Report Error Discuss

3 202
Q:

X and Y can complete a work in 5 days. Y and Z can complete the same work in 6 days. Z and X can complete the same work in 15/2 days. In how many days will X, Y and Z together complete the work?

 

A) 2   B) 4  
C) 3   D) 2/5
 
Answer & Explanation Answer: B) 4  

Explanation:
Report Error

View Answer Report Error Discuss

4 195
Q:

Ram and Shyam can complete a task in623 days and 15 days, respectively. They work together for 4 days, and then Ram leaves. In how many days after Ram leaves, will Shyam complete the remaining task alone?

 

A) 112days B) 3 days
C) 4 days D) 2 days
 
Answer & Explanation Answer: D) 2 days

Explanation:
Report Error

View Answer Report Error Discuss

1 246
Q:

X and Y can do a piece of work in 10 days, Y and Z in 12 days and Z and X in 15 days. In how many days can Z alone do the work?

 

A) 40 B) 24
C) 18 D) 36
 
Answer & Explanation Answer: A) 40

Explanation:
Report Error

View Answer Report Error Discuss

0 178
Q:

A and B can complete a piece of work together in 20 days. They start work together but A had to leave 5 days before the work finally got over. If B finishes the remaining in 18 days, then how long will A take to complete the work separately.

 

A) 100 days B) 120 days
C) 72 days D) 64 days
 
Answer & Explanation Answer: D) 64 days

Explanation:
Report Error

View Answer Report Error Discuss

0 297