4
Q:

A shopkeeper has a job to print certain number of documents and there are three machines P, Q and R for this job. P can complete the job in 3 days, Q can complete the job in 4 days and R can complete the job in 6 days. How many days the shopkeeper will it take to complete the job if all the machines are used simultaneously ?

A) 4/3 days B) 2 days
C) 3/2 days D) 4 days

Answer:   A) 4/3 days



Explanation:

Let the total number of documents to be printed be 12.

 The number of documents printed by P in 1 day = 4.

 The number of documents printed by Q in 1 day = 3.

 The number of documents printed by R in 1 day = 2.

 
Thus, the total number of documents that can be printed by all the machines working simultaneously in a single day = 9.

 

Therefore, the number of days taken to complete the whole work = 12/9 = 4/3 days.

Q:

A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for ₹35000. The share of A (in ₹) in the contracted money will be:

 

A) 7000 B) 21000
C) 14000 D) 15000
 
Answer & Explanation Answer: C) 14000

Explanation:
Report Error

View Answer Report Error Discuss

4 391
Q:

A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for ₹35000. The share of B (in ₹) in the contracted money will be:

 

A) ₹15000 B) ₹14000
C) ₹21000 D) ₹7000
 
Answer & Explanation Answer: C) ₹21000

Explanation:
Report Error

View Answer Report Error Discuss

0 325
Q:

A and B can complete a piece of work in 15 days and 10 days respectively. They got a contract to complete the work for ₹75000. The share of B (in ₹) in the contracted money will be:

 

A) 45,000 B) 30,000
C) 35,000 D) 40,000
 
Answer & Explanation Answer: A) 45,000

Explanation:
Report Error

View Answer Report Error Discuss

1 423
Q:

If 16 men working 12 hours a day can complete a work in 27 days, then working for how many hours a day can 18 men complete the work in 24 days ?

 

A) 9 B) 18
C) 16 D) 12
 
Answer & Explanation Answer: D) 12

Explanation:
Report Error

View Answer Report Error Discuss

1 969
Q:

If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days?

 

A) 50 B) 60
C) 54 D) 45
 
Answer & Explanation Answer: B) 60

Explanation:
Report Error

View Answer Report Error Discuss

2 461
Q:

A can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many dayscan they finish 50% of the work, if they work together

 

A) 12 B) 6
C) 8 D) 9
 
Answer & Explanation Answer: B) 6

Explanation:
Report Error

View Answer Report Error Discuss

3 689
Q:

Shyam can complete a task in 12 days by working 10 hours a day. How many hours a day should he work to complete the task in 8 days?

 

A) 12 B) 15
C) 16 D) 14
 
Answer & Explanation Answer: B) 15

Explanation:
Report Error

View Answer Report Error Discuss

1 811
Q:

5 men and 8 women can complete a task in 34 days, whereas 4 men and 18 women can complete the same task in 28 days. In how many days can the same task be completed by 3 men and 5 women?

 

A) 56 B) 72
C) 64 D) 36
 
Answer & Explanation Answer: A) 56

Explanation:
Report Error

View Answer Report Error Discuss

6 994