Questions

Q:

Guess which number should be replaced by the "?" in the given series 0,10,1110,3110,132110,?

Answer

1113122110


In given series 2nd number gives number of  which digits present in the 1st number and so on continues for 3rd ,4th,...


Here 1st no. has only one zero, so  2nd no. is 10 and 2nd no. has one 1 and one 0,so 3rd no. is 1110, so like that 5th no. has one 1,one 3,one 2,two 1's and one 0.So the next no. is 1113122110. 


 

Report Error

View answer Workspace Report Error Discuss

Subject: Math Puzzles Exam Prep: CAT
Job Role: Bank PO

13 4392
Q:

Select the correct statement about the pharynx.

A) The auditory tube drains into the nasopharynx B) The laryngopharynx blends posteriorly into the nasopharynx
C) The palatine tonsils are embedded in the lateral walls of the nasopharynx D) The pharyngeal tonsil is located in the laryngopharynx
 
Answer & Explanation Answer: A) The auditory tube drains into the nasopharynx

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: Biology
Exam Prep: AIEEE , Bank Exams
Job Role: Analyst , Bank Clerk , Bank PO

3 4392
Q:

What is the assigned code name of India first nuclear explosion at Pokran ?  

A) Operation Sakshi B) Operation Hurricane
C) Operation smiling Buddha D) Operation cross road
 
Answer & Explanation Answer: C) Operation smiling Buddha

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness

3 4390
Q:

Harmful bacteria in drinking water cannot be destroyed by 

A) Chlorination B) boiling
C) adding caustic soda D) ozonisation
 
Answer & Explanation Answer: C) adding caustic soda

Explanation:

Water containing caustic soda cannot be used for drinking

Report Error

View Answer Report Error Discuss

Filed Under: Chemistry

1 4389
Q:

An important tool for project scope management is

A) Fast tracking B) Work breakdown structure
C) Crashing D) A Gantt Chart
 
Answer & Explanation Answer: B) Work breakdown structure

Explanation:

Work breakdown structure is an important tool for project scope management.

 

Project Scope Management refers to the set of processes that ensure a project’s scope is accurately defined and mapped. Scope Management techniques enable project managers and supervisors to allocate just the right amount of work necessary to successfully complete a project—concerned primarily with controlling what is and what is not part of the project’s scope.

Report Error

View Answer Report Error Discuss

14 4389
Q:

The shortest air route from Moscow to San Francisco is

A) Over the Atlantic Ocean B) Over the Pacific via Siberia
C) Over the North Pole D) Through the latitude which passes through them
 
Answer & Explanation Answer: A) Over the Atlantic Ocean

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: World Geography

5 4388
Q:

Which of the following is an example of representative money?

A) Salt B) A tract of land
C) Gold D) A check
 
Answer & Explanation Answer: D) A check

Explanation:

Representative money is an item such as a token or piece of paper that has no intrinsic value but can be exchanged on demand for a commodity that does have intrinsic value, such as gold, silver, copper,...

 

Hence, a Check is an example of representative money.

Report Error

View Answer Report Error Discuss

Filed Under: Indian Economy
Exam Prep: AIEEE , Bank Exams , CAT
Job Role: Analyst , Bank Clerk , Bank PO

9 4388
Q:

The Supreme Court has reconstituted the special Investigation Team(SIT) to expedite probe into Black Money Cases and directed the government to issue the necessary notification. Who of the following is the chairman of this team?

A) Arijit Pasayat B) M.B.Shah
C) R.M.Lodha D) Vinod Rai
 
Answer & Explanation Answer: B) M.B.Shah

Explanation:
Report Error

View Answer Report Error Discuss

Filed Under: General Awareness

3 4388