Certification Questions

Q:

A large CRM project took place last year included hundreds of meetings between the various key users. All of the conversations were save in a single Word 2010 document. You need to find all instances of the following words 'bleed' and 'bled'. Which of the following wildcard searches would be best?

A) ble{2}d B) ble{1,}d
C) ble{e2}d D) ble[e2]d
 
Answer & Explanation Answer: B) ble{1,}d

Explanation:
Report Error

View Answer Report Error Discuss

2 2161
Q:

In the case of the valuation of time wage types, if the RTE or AMT field contains an amount, the wage type is transferred to the internal table...

A. RF.

B. OT.

C. KX.

D. CT.

Answer

Answer : B

Report Error

View answer Workspace Report Error Discuss

Subject: SAP HR

0 2160
Q:

Project Time Management - Processes

Describe the Inputs, Tools and Techniques, Outputs of Schedule Development?

Answer

I. Inputs



  • Organizational process assets

  • Project scope statement

  • Activity list

  • Activity attributes

  • Project schedule network diagrams

  • Activity resource requirements

  • Resource calendars

  • Activity duration estimates 

  • Project management plan


                - RisK register


II. Tools and Techniques



  • Schedule network analysis

  • Critical path method

  • Schedule compression

  • What-if scenario analysis

  • Resource leveling

  • Critical chain method

  • Project management software

  • Applying calendars

  • Adjusting leads and lags 

  • Schedule model


III. Outputs



  • Project schedule

  • Schedule model data

  • Schedule baseline

  • Resource requirements (updates)

  • Activity attributes (updates)

  • Project calendar (updates)

  • Requested changes

  • Project management plan (updates)


                 - Schedule management plan(updates)

Report Error

View answer Workspace Report Error Discuss

0 2159
Q:

Project Human Resource Management

What are the Project Management Processes included in the Project Human Resource Management?

Answer

Human Resource Planning - Identifying and documenting Project roles, responsibilities, and reporting relationships, as well as creating the staffing management plan.


Acquire Project Team - Obtaining the human resources needed to complete the project


Develop Project Team - Improving the competencies and interaction of team members to enhance project performance.


Manage Project Team - Tracking team member performance, providing feedback, resolving issues, and coordinating changes to enhance project performance.

Report Error

View answer Workspace Report Error Discuss

0 2158
Q:

Project Scope Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Scope Verification ?

Answer

I. Inputs



  • Project scope statement

  • WBS dictionary

  • Project scope management plan

  • Deliverables


II. Tools and Techniques



  • Inspection


III. Outputs



  • Accepted  deliverables

  • Requested changes

  • Recommended corrective actions

Report Error

View answer Workspace Report Error Discuss

0 2151
Q:

Before you can create cost centers, you must first create a _______ heirarchy.

A. Logical

B. Optimum

C. Complete

D. Standard

Answer

Answer : D

Report Error

View answer Workspace Report Error Discuss

Subject: SAP CO

0 2145
Q:

Project Communications Management

What are the Project Management Processes included in the Project Communications Management?

Answer

Communications planning - Determining the information and communications needs of the project stakeholders.


Information Distribution - Making needed information available  to project stakeholders in a timely manner.


Performance Reporting - Collecting and distributing performance information. This includes status reporting, progress measurement, and forecasting.


Manage Stakeholders - Managing communications to satisfy the requirements of and resolve issues with project stakeholders.

Report Error

View answer Workspace Report Error Discuss

0 2142
Q:

Project Quality Management - Processes

Describe the Inputs, Tools and Techniques , Outputs included in the Perform Quality Assurance?

Answer

I. Inputs



  • Quality management plan

  • Quality metrics

  • Process improvement plan 

  • Work performance information 

  • Approved change requests

  • Quality control measurements 

  • Implemented change requests

  • Implemented corrective actions 

  • Implemented defect repair

  • Implemented preventive actions 


II. Tools and Techniques



  • Quality planning tools and techniques

  • Quality audits

  • Process analysis 

  • Quality control tools and techniques


III. Outputs



  • Requested changes

  • Recommended corrective actions

  • Organizational process assets (updates)

  • Project management plan (updates)

Report Error

View answer Workspace Report Error Discuss

0 2142